DOW JONES NEWSWIRES
The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.
Total Petrochemicals USA on April 22 began the process of restarting its Port Arthur, Texas, refinery; the plant was shut on March 24 for economic reasons. Starting at about 5:00 a.m. CDT, 18 units will be restarted in an orderly fashion; the process is expected to end at around the same time on April 28.
ConocoPhillis on April 21 said that planned maintenance is on-going at its Rodeo, Calif., refinery. A hydrocracking unit and reformer were taken out of service in early March for what was expected to be 45-days of scheduled work.
Marathon Oil on April 21 said that crude oil throughput has been reduced at its Catlettsburg, Kentucky, refinery since April 17 due to a crude oil delivery pipeline leak. The company has allocated product deliveries to its customers within the area which will be lifted when the refinery resumes normal crude rates.
Delek US Holdings (DK) on APril 21 began the sequential restart of all processing units at its Tyler, Texas, refinery following a fatal fire and explosion on Nov. 20, 2008.
Total Petrochemicals USA (TOT) on Aparil 20 restarted a steam boiler at its shuttered Port Arthus refinery; it was not clear whether the boiler restart signaled the start-up of other process units. The refinery has been shuttered for economic reasons since March 24.
ConocoPhillips (COP) on April 20 began four days of work at two FCCUs at its Borger, Texas, refinery to replace electronic cards associated with electrostatic precipitator rappers. It was not clear whether the work will impact production.
BP began work on April 20 at a key gasoline-making unit at its Texas City, Texas, refinery. FCCU 1 will undergo two days of maintenance on the Electrostatic Precipitator Stack starting at 8:00 a.m. on Monday. The work will not impact production at the plant, a source familiar with operations said.
On April 17, Valero Energy Corp. (VLO) said it was planning maintenance on a hydrotreater at its Port Arthur, Texas, refinery. The company didn't specify when or how long the maintenance would last.
Planned work at ConocoPhillips' (COP) Wood River, Ill., refinery was completed late last week, the company said April 14. In an email, he said that planned maintenance is ongoing at the company's Billings, Mont., and San Francisco area refineries.
The Illinois refinery, which is a joint venture with EnCana Corp. (ECA), has a capacity of 306,000 barrels a day.
On April 13, a power trip at the Valero Energy Corp. (VLO) Texas City refinery caused flaring, according to a report with the Texas Commission on Environmental Quality. The report did not say if production was impacted. The refinery has a capacity of 199,500.
A power outage shut down the west plant at the Citgo Corpus Christi, Texas refinery over the weekend, according to a state environmental filing.
The power blip occurred at 10:12 p.m. Saturday CT, according to the report from the Texas Commission on Environmental Quality. The refinery is back to normal, the company said April 13.
For more detailed information, search Dow Jones Newswires using the code N/REF.
Operator Refinery Capacity Description Restart (in 000s bbl/day) EAST COAST Valero Delaware 210.0 Boiler system inspection and May 3 City, DE repair extends refinery down- time by one mo. to early May. Entire refinery shut Mar. 4 for 30 days maintenance at coker unit which has been shuttered since Feb. 15. FCCU at reduced rates since n/a mid-Dec. for economic reasons. CARIBBEAN GULF COAST Citgo Corpus 156.0 April 11 power outage shuts West plant. April 14 SRU restarted. Back to normal, Co. said April 14. Conoco Belle Chasse 247.0 Power outage April 5 mid-April La. shuts refinery Conoco Borger, TX 152.0 Conoco Sweeny Tx 247.0 Fire partially shuts coker unit April 9th Delek US Tyler, TX 60.0 Refinery expected to be wholly May on-line by May 2009, following Nov. 20 fire at sat. gas unit killed two workers and injured others. Flint Hills Corpus, 288.1 Shut SRU #2 April 5 for work April 7 Christi, Tx Valero Port Arthur 325.0 FCCU at reduced rates since n/a TX mid-Dec. for economic rea- sons. Shut hydrocracker for repairs April 3. April 10-13 MIDWEST Marathon Catlettsburg 226.0 Refinery at reduced rates n/a KY since Apr. 17 owing to crude oil delivery pipe- line leak. No estimate on return to normal opera- tions. ROCKY MOUNTAINS Sinclair Sinclair, 66.0 Refinery opps at 50% mid-April WY after March fire. WEST COAST Flint North Pole 210.0 One of three processing n/a Hills units has been shut due to low jet fuel demand, the co. confirmed on Mar. 19. PetroStar Valdez, AK 48.0 Refinery shut due to Dec. n/a 28 fire. PLANNED CANADA North Newfound- 115.0 Plantwide shutdown will begin Early Atlantic land first week of April for 21 May days of planned maintenance. Upgrade work at hydrotreater will take an additional 14 days. EAST COAST Conoco Linden 238.0 145,000-b/d FCCU shut Feb. April 3 NJ 18 for about 45 days of planned turnaround mainte- nance. In Restart April 3. Sunoco Philadelphia 330.0 Reformer unit shut in early n/a PA Oct. for economic reasons. Shutdown to last one to six months. Valero Delaware 210.0 82,000-b/d FCCU operating n/a DE at reduced rate for eco- nomic reasons, Co. said on Dec. 16. Valero Paulsboro 160.0 27,000-b/d coker unit to n/a NJ shut in April for 35-days of planned work, the Co. said on Mar. 11. GULF COAST Chevron Pascagoula 330.0 Pre-commercial heavy oil 2010 Miss. conversion project delayed from 2008 to 2010 due to economic factors. Flint Corpus 288.1 $250 mil. project for new Spr Hills Christi, TX diesel desulfurization, 2010 sulfur recovery unit to begin in Fall 2008. Construction to last 18 months. Marathon Garyville 245.0 Project to increase crude oil 4Q LA refining capacity by 180,000- 2009 b/d expected to conclude in 4th-quarter, 2009. Marathon Texas City 76.0 Platformer and UDEX shut for n/a TX annual planned maintenance and catalyst change on Feb. 4. Total Port Arthur 232.0 Refinery in restart mode; 18 Apr 22 units will be sequentially restarted starting at about 5:00 a.m. CDT on Apr. 22. The process is expected to conclude on Apr. 28. The units shut due to poor economic con- ditions on Mar. 24 Valero Corpus 340.0 20,000-b/d FCCU in East n/a Plant shut; West Plant 50,000-b/d FCCU at reduced rates since mid-Dec. for economic reasons. Valero McKee, TX 170.0 Smaller of two crude units May/ at 60,000-b/d to shut in June May for 14 days; 55,000-b/d to shut in May for 21 days. Valero Norco, LA 250.0 Upgrade project to build 2012 a new diesel hydrotreater unit moved from 2010 to
4th-quarter 2012, the Co. said on Jan. 27. Valero Port Arthur 325.0 77,000-b/d FCCU at reduced n/a TX rates since mid-Dec. for economic reasons. A Hydrotreater was taken down for planned work April 17 Valero Sunray, TX 170.0 55,000-b/d FCCU at reduced n/a rates since mid-Dec. for economic reasons. Valero Three Rivers 95.0 24,000-b/d FCCU at reduced n/a TX rates since mid-Dec. for economic reasons. MID-WEST BP Whiting, 410.0 Planned maintenane continues End IN on Mar. 16 at the smaller of Mar 3 crude units. The work began in early March and is expected Early to conclude by the end of the Apr month or by early April. Frontier El Dorado 130.0 Hydrotreater in restart and Mar. KS expected to produce product by 28-29 Mar. 28-29, the Co. said. A coker turnaround and expan- Mid- sion project was delayed until Aug. Mid-July, and subsequently delayed until August. Marathon Robinson 204.0 Crude unit, two coker units Mid- shut Mar. 9 restarted mid- Apr. April. Sunoco Toledo, OH 160.0 FCCU turnaround lasting 6 weeks 4Q08 planned for 4q 2008 or 1Q 2009 Sunoco Tulsa, Okla. 85.0 Turnaround maintenance will n/a take place in Feb., the Co. said on Feb. 5. Refinery could close by end of 2009 if buyer not found. Valero Memphis, TN 195.0 FCCU upgrade originally slated 2012 for completion in 2009 has been shifted to 2012, the Co. said on Jan. 27. ROCKY MOUNTAINS Conoco Billings, 61.0 On Mar. 5 the Co. delayed for Jan. MT one year an expansion project 2010 which will increase capacity to 71,000 bbls. Construction of a new crude is now scheduled to begin in January 2010. Co. said April 14 that planed work was ongoing at the refinery. Co. did not give more specifics. Frontier Cheyenne 52.0 The refinery is operating at n/a WY reduced rates for economic reasons. Suncor Commerce City 90.0 32,000-b/d crude unit, n/a CO 10,500-b/d reformer will shut in March for planned maintenance, the Co. said on Jan. 26. WEST COAST Alon Paramount 55.0 Hydrocracker project post- CA poned indefinitely, the Co. said on Feb. 4 Conoco Rodeo, CA 153.5 Work continues at hydro- n/a cracker and reformer units. 45 days of planned work was expected to conclude by Apr. 15. No restart estimate. Valero Benicia 144.0 Hydrocracker in restart April Apr 2 CA 2 after two-week turnaround. Back to planned rates, co. Apr 6 said.
1 Year Casino Guichard Perrachon Chart |
1 Month Casino Guichard Perrachon Chart |
It looks like you are not logged in. Click the button below to log in and keep track of your recent history.
Support: +44 (0) 203 8794 460 | support@advfn.com
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions