We could not find any results for:
Make sure your spelling is correct or try broadening your search.
Share Name | Share Symbol | Market | Type | Share ISIN | Share Description |
---|---|---|---|---|---|
Nighthawk | LSE:HAWK | London | Ordinary Share | GB00B156TD53 | ORD 0.25P |
Price Change | % Change | Share Price | Bid Price | Offer Price | High Price | Low Price | Open Price | Shares Traded | Last Trade | |
---|---|---|---|---|---|---|---|---|---|---|
0.00 | 0.00% | 0.115 | 0.00 | 01:00:00 |
Industry Sector | Turnover | Profit | EPS - Basic | PE Ratio | Market Cap |
---|---|---|---|---|---|
0 | 0 | N/A | 0 |
TIDMHAWK
RNS Number : 9225N
Nighthawk Energy plc
01 November 2016
1 November 2016
NIGHTHAWK ENERGY PLC
("Nighthawk" or "the Company")
Water Flood Pilot Project Update
Nighthawk, the US focused oil development and production company (AIM: HAWK and OTCQX: NHEGY), announces an update to the Company's Arikaree Creek water flood pilot project (the "Pilot Project").
Pilot Project Development Update
As previously disclosed, the Pilot Project was anticipated to begin operations in late October 2016, however this is now expected to be pushed back until mid-November 2016.
On 28 October 2016, the Company performed a mechanical integrity test ("MIT") on the injection wells and were notified that it did not pass state specifications. Therefore, the Company will carry out remediation work on the two injection wells to rectify the pressure drain-offs experienced. The Company expects to be able to pass the state testing, depending on the required solution, in 7 to 14 days.
This is the last remaining step to complete to bring the project online. All other construction and testing has been completed and injection equipment has been installed, ready to commence operations.
In order to comply with the terms of the Company's arrangement with its commercial lender, Commonwealth Bank of Australia ("CBA"), on 31 October 2016 the Company signed an amendment with CBA, regarding project milestones, included in the 4(th) Amendment to the credit agreement which required water flood injection to commence by 31 October 2016 as well as initial well response by that date. The further amendment extends the water flood injection date to 15 November 2016 and initial well response to 30 November 2016. The Company anticipates meeting both these amended threshold dates.
Rick McCullough, Chairman of Nighthawk, commented:
"The MIT testing that was not passed on the two injector wells only related to the wells holding pressure and is, from a technical standpoint, relatively easy to fix but does require the time to re-enter the well. Our operations team immediately began workover efforts following the test results and we are confident we will have the Pilot Project up and running within two weeks. This delay will not have a significant impact on either the revenues or volumes produced from the project."
Enquiries:
Nighthawk Energy plc Rick McCullough, Chairman +1 303 407 9600 Kurtis Hooley, Chief Financial Officer +44 (0) 20 3582 1350 Stockdale Securities Limited +44 (0) 20 7601 6100 Richard Johnson David Coaten
This announcement contains inside information for the purposes of Article 7 of Regulation (EU) 596/2014.
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCDFLFXQBFEFBF
(END) Dow Jones Newswires
November 01, 2016 03:00 ET (07:00 GMT)
1 Year Nighthawk Energy Chart |
1 Month Nighthawk Energy Chart |
It looks like you are not logged in. Click the button below to log in and keep track of your recent history.
Support: +44 (0) 203 8794 460 | support@advfn.com
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions