ADVFN Logo ADVFN

We could not find any results for:
Make sure your spelling is correct or try broadening your search.

Trending Now

Toplists

It looks like you aren't logged in.
Click the button below to log in and view your recent history.

Hot Features

Registration Strip Icon for default Register for Free to get streaming real-time quotes, interactive charts, live options flow, and more.

KIM Kimcor

0.325
0.00 (0.00%)
17 May 2024 - Closed
Delayed by 15 minutes
Share Name Share Symbol Market Type Share ISIN Share Description
Kimcor LSE:KIM London Ordinary Share GB00B0TNHV95 ORD 0.5P
  Price Change % Change Share Price Bid Price Offer Price High Price Low Price Open Price Shares Traded Last Trade
  0.00 0.00% 0.325 0.00 01:00:00
Industry Sector Turnover Profit EPS - Basic PE Ratio Market Cap
0 0 N/A 0

Newlands Update

25/03/2008 12:33pm

UK Regulatory


RNS Number:7014Q
KimCor Diamonds plc
25 March 2008

                                                                   25 March 2008



                              KimCor Diamonds plc

                          ("KimCor" or the "Company")



                    NEWLANDS PROCESSING PLANT COMMISSIONING



KimCor Diamonds plc ("KimCor" or the "Company" or the "Group"), a diamond
producer and exploration company with properties in South Africa and Tanzania,
is pleased to announce that the expansion and upgrade of the Newlands diamond
mine processing plant has been completed.



HIGHLIGHTS



*        Commissioning of the plant commenced on 25 March;

*        The plant is quickly expected to reach its new capacity of 37,000
         tonnes per month ("tpm");

*        Plant capacity has been increased from 4,500 tpm to 37,000 tpm;

*        The plant will process 7,000 tonnes of kimberlite ore with an average
         grade of 23 carats per hundred tonnes ("cpht"); and

*        The plant will process 30,000 tonnes of tailings stockpile with an
         average grade of 7 cpht.



The expanded plant design includes a new crushing circuit which will crush
kimberlite ore to 6mm for improved diamond recovery.



In addition to plant expansion, mine management have completed shaft deepening
and underground development to access and mine increased tonnage of kimberlite
ore. Further underground development will continue to year end at which time
kimberlite mining and processing is expected to increase to 15,000 tpm.



Martyn Churchouse, Chief Executive Officer commented "The local management team
continues to meet both its scheduled completion dates and capital budgets on the
various mine and processing plant upgrades and expansions. This is particularly
the case with Newlands as the same team have simultaneously completed the Phase
One expansion at SMI4.



"We have now provided the Newlands mine management with the infrastructure it
requires to significantly increase mine production and we have set targets that
will see the mining and processing of underground ores double during 2009".





Enquiries:



KimCor Diamonds plc                                           Tel: 020 3178 6179
Martyn Churchouse


Strand Partners Limited                                       Tel: 020 7409 3494
Simon Raggett
Warren Pearce
Victoria Milne-Taylor


Bishopsgate Communications Ltd                                Tel: 020 7562 3350
Maxine Barnes
Nick Rome












                      This information is provided by RNS
            The company news service from the London Stock Exchange