![](/cdn/assets/images/search/clock.png)
We could not find any results for:
Make sure your spelling is correct or try broadening your search.
Share Name | Share Symbol | Market | Type | Share ISIN | Share Description |
---|---|---|---|---|---|
Prospex Energy Plc | AQSE:PXEN.GB | Aquis Stock Exchange | Ordinary Share | GB00BMFZVZ53 |
Price Change | % Change | Share Price | Bid Price | Offer Price | High Price | Low Price | Open Price | Shares Traded | Last Trade | |
---|---|---|---|---|---|---|---|---|---|---|
0.00 | 0.00% | 8.75 | 8.00 | 9.50 | 9.35 | 7.45 | 8.75 | 362,848 | 16:29:57 |
Industry Sector | Turnover | Profit | EPS - Basic | PE Ratio | Market Cap |
---|---|---|---|---|---|
0 | 0 | N/A | 0 |
TIDMPXEN
RNS Number : 1056U
Prospex Energy PLC
01 December 2021
Prospex Energy PLC / Index: AIM / Epic: PXEN / Sector: Oil and Gas
1 December 2021
Prospex Energy PLC
El Romeral: Update on plant optimisation project
Prospex Energy PLC, ('Prospex' or the 'Company') the AIM quoted investment company (AIM: PXEN) focused on European gas and power projects, provides an update on the El Romeral plant optimisation project in southern Spain, in which the Company holds a 49.9% working interest, through its interest in Tarba Energía.
The plant optimisation programme was delayed by computer technology supply chain issues which have since been addressed. The last items of equipment necessary to automate plant operations arrived to allow the plant automation upgrades to commence on 21 November 2021. After some technical issues were encountered with the installation of the new control systems and the completion of a run-in and optimisation programme, the plant upgrades have been successfully integrated. As a result of these actions the plant recommenced continuous stable electricity generation on 26 November 2021.
The El Romeral power plant can now be operated 24 hours a day, 7 days a week, switching between the two operational generators as required. Continuous operations resulting from this system optimisation project may allow an increase in power generation income of up to 65%. With the installation of the new remote monitoring and control systems, the plant can now be run with reduced manual intervention, thereby also reducing the overhead and the operational expenditure of the project. In addition to this, reservoir management is also optimised because a constant flow of gas from a gas well is preferable to shutting in production every week as the plant was hitherto not usually operational on a Sunday.
Mark Routh Prospex's CEO commented:
"Whilst it is frustrating that the global semiconductor supply shortages delayed the start of this optimisation programme, I am very pleased to report that the project has now completed safely and on budget. We will of course continue to monitor the performance of the plant and the gas reservoirs very closely and will record the performance statistics of the expected increased power generation capacity, which I expect to share at the next operational update."
This announcement contains inside information for the purposes of Article 7 of the Market Abuse Regulation (EU) 596/2014 as it forms part of UK domestic law by virtue of the European Union (Withdrawal) Act 2018 ("MAR") and is disclosed in accordance with the Company's obligations under Article 17 of MAR.
* * ENDS * *
For further information visit www.prospex.energy or contact the following:
Mark Routh Prospex Energy PLC Tel: +44 (0) 20 7236 1177 Rory Murphy Strand Hanson Limited Tel: +44 (0) 20 7409 Ritchie Balmer 3494 Colin Rowbury Novum Securities Limited Tel: +44 (0) 20 7399 Jon Belliss 9427 Duncan Vasey Peterhouse Capital Tel: +44 (0) 20 7220 Limited 9797 Susie Geliher St Brides Partners Tel: +44 (0) 20 7236 Catherine Leftley Ltd 1177
This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
END
UPDFZMFMNGZGMZM
(END) Dow Jones Newswires
December 01, 2021 02:00 ET (07:00 GMT)
1 Year Prospex Energy Chart |
1 Month Prospex Energy Chart |
It looks like you are not logged in. Click the button below to log in and keep track of your recent history.
Support: +44 (0) 203 8794 460 | support@advfn.com
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions