We could not find any results for:
Make sure your spelling is correct or try broadening your search.
Share Name | Share Symbol | Market | Type |
---|---|---|---|
Itafos Inc | TSXV:IFOS | TSX Venture | Common Stock |
Price Change | % Change | Share Price | Bid Price | Offer Price | High Price | Low Price | Open Price | Shares Traded | Last Trade | |
---|---|---|---|---|---|---|---|---|---|---|
-0.02 | -1.16% | 1.71 | 1.71 | 1.73 | 1.73 | 1.71 | 1.73 | 25,915 | 21:01:01 |
David Delaney, Chief Executive Officer, commented, “The Notice to Proceed is the final approval step to allow us to achieve our strategic goal of extending Conda’s mine life with H1 / NDR. Itafos, and the Conda community, would like to thank the Bureau of Land Management, the U.S. Forest Service and all the other regulatory agencies for their diligent and collaborative work on this project. The Itafos team at Conda is quickly mobilizing resources and operations to begin the development of H1/NDR.”
About Itafos
The Company is a phosphate and specialty fertilizer company. The Company’s businesses and projects are as follows:
The Company’s shares trade on the TSX Venture Exchange (“TSX-V”) under the ticker symbol “IFOS”.
For more information, or to join the Company’s mailing list to receive notification of future news releases, please visit the Company’s website at www.itafos.com.
Scientific and Technical Information
Note (1) – Timeline for Husky 1 / North Dry Ridge based on management estimates and subject to certain assumptions, including successful permitting and development activities. The Husky 1 / North Dry Ridge mine life extension is based on a Preliminary Economic Assessment (“2019 PEA”) included in the Conda Technical Report (as defined below). The 2019 PEA on the H1 and NDR properties is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the 2019 PEA will be realized. Readers are referred to the Conda Technical Report for the applicable qualifications and assumptions in connection with its 2019 PEA.
The scientific and technical information contained in this news release related to Mineral Resources for Conda has been reviewed and approved by Jerry DeWolfe, Professional Geologist (P.Geo.) with the Association of Professional Engineers and Geoscientists of Alberta. Mr. DeWolfe is a full-time employee of WSP Canada Inc. and is independent of the Company. The scientific and technical information contained in this news release related to Mineral Reserves for Conda has been reviewed and approved by Edward Minnes, Professional Engineer (P.E.) licensed by the State of Missouri. Mr. Minnes is a part-time employee of WSP USA Inc. and is independent of the Company. The Company’s latest technical report in respect of Conda is entitled, “NI 43-101 Technical Report on Itafos Conda and Paris Hills Mineral Projects, Idaho, USA,” with an effective date of July 1, 2019 (the “Conda Technical Report”) and is available under the Company’s website at www.itafos.com and under the Company’s profile on SEDAR at www.sedar.com.
Forward-Looking Information
Certain information contained in this news release constitutes forward-looking information, including statements with respect to the timing for commencement of operations at H1 / NDR, the expected resource life of H1 / NDR and the sources of funding to be used for the development of H1 / NDR. All information other than information of historical fact is forward- looking information. The use of any of the words “intend”, “anticipate”, “plan”, “continue”, “estimate”, “expect”, “may”, “will”, “project”, “should”, “would”, “believe”, “predict” and “potential” and similar expressions are intended to identify forward- looking information. This information involves known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking information.
The FLI contained in this news release is based on the opinions, assumptions and estimates of management, including those set out herein, which management believes are reasonable as at the date the statements are made. Those opinions, assumptions and estimates are inherently subject to a variety of risks and uncertainties and other known and unknown factors that could cause actual events or results to differ materially from those projected in the FLI. These include the Company’s expectations and assumptions with respect to the following: commodity prices; operating results; safety risks; changes to the Company’s mineral reserves and resources; risk that timing of expected permitting will not be met; changes to mine development, optimization plans and completion; foreign operations risks; changes to regulation; environmental risks; the impact of adverse weather and climate change; general economic changes, including inflation and foreign exchange rates; the actions of the Company’s competitors and counterparties; financing, liquidity, credit and capital risks; the loss of key personnel; impairment risks; cybersecurity risks; risks relating to transportation and infrastructure; changes to equipment and suppliers; adverse litigation; changes to permitting and licensing; loss of land title and access rights; changes to insurance and uninsured risks; the potential for malicious acts; market volatility; changes to technology; changes to tax laws; the risk of operating in foreign jurisdictions; and the risks posed by a controlling shareholder and other conflicts of interest. Readers are cautioned that the foregoing list of risks, uncertainties and assumptions is not exhaustive.
Although the Company has attempted to identify crucial factors that could cause actual actions, events or results to differ materially from those described in FLI, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Additional risks and uncertainties affecting the FLI contained in this news release are described in greater detail in the Company’s current Annual Information Form and current Management’s Discussion and Analysis available under the Company’s profile on SEDAR at www.sedar.com and on the Company’s website at www.itafos.com. There can be no assurance that FLI will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. The reader is cautioned not to place undue reliance on FLI. The Company undertakes no obligation to update forward-looking statements if circumstances or management’s estimates, assumptions or opinions should change, except as required by applicable securities law. The FLI included in this news release is expressly qualified by this cautionary statement and is made as of the date of this news release.
NEITHER THE TSX-V NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX-V) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS NEWS RELEASE.
For further information, please contact:
Matthew O’NeillItafos Investor Relations investor@itafos.com 713-242-8446
1 Year Itafos Chart |
1 Month Itafos Chart |
It looks like you are not logged in. Click the button below to log in and keep track of your recent history.
Support: +44 (0) 203 8794 460 | support@advfn.com
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions