We could not find any results for:
Make sure your spelling is correct or try broadening your search.
Share Name | Share Symbol | Market | Type | Share ISIN | Share Description |
---|---|---|---|---|---|
Central Asia Metal PLC | AQSE:CAML.GB | Aquis Stock Exchange | Ordinary Share | GB00B67KBV28 | Common Stock10p |
Price Change | % Change | Share Price | Bid Price | Offer Price | High Price | Low Price | Open Price | Shares Traded | Last Trade | |
---|---|---|---|---|---|---|---|---|---|---|
-3.00 | -1.92% | 153.00 | 148.00 | 158.00 | 153.00 | 153.00 | 153.00 | 0.00 | 06:58:39 |
Industry Sector | Turnover | Profit | EPS - Basic | PE Ratio | Market Cap |
---|---|---|---|---|---|
0 | 0 | N/A | 0 |
TIDMCAML
RNS Number : 2440C
Central Asia Metals PLC
10 October 2022
10 October 2022
CENTRAL ASIA METALS PLC
('CAML' or the 'Company')
Q3 2022 Operations Update
Central Asia Metals plc (AIM: CAML) today provides a Q3 2022 operations update for the Kounrad dump leach, solvent extraction and electro-winning ('SX-EW') copper recovery plant in Kazakhstan ('Kounrad') and the Sasa zinc-lead mine in North Macedonia ('Sasa').
Summary
-- No lost time injuries ('LTIs') at either Kounrad or Sasa during Q3 2022 -- Kounrad
o Q3 2022, 4,067 tonnes of copper produced
o First nine months of 2022, 10,685 tonnes of copper produced
-- Sasa
o Q3 2022 zinc in concentrate, 5,746 tonnes produced
o Q3 2022 lead in concentrate, 6,899 tonnes produced
o First nine months of 2022 zinc in concentrate, 16,211 tonnes produced
o First nine months of 2022 lead in concentrate, 20,726 tonnes produced
Outlook
-- On course to achieve increased 2022 guidance for Kounrad's copper production (13,500 to 14,000 tonnes)
-- On course to meet Sasa 2022 production guidance
o Zinc in concentrate, 20,000-22,000 tonnes
o Lead in concentrate, 27,000-29,000 tonnes
CAML production summary
Metal production (tonnes) Q3 2022 Q2 2022 Q1 2022 9m 2022 9m 2021 Copper 4,067 3,593 3,024 10,685 10,360 -------- -------- -------- -------- -------- Zinc 5,746 5,225 5,240 16,211 17,033 -------- -------- -------- -------- -------- Lead 6,899 7,091 6,736 20,726 20,734 -------- -------- -------- -------- --------
Nigel Robinson, Chief Executive Officer, commented:
"I am pleased to report safe and strong production from both of our operations during Q3 2022, with zero LTIs. At Kounrad, we announced increased 2022 production guidance with our H1 2022 results, and we are on track to deliver this and meet our production targets at Sasa.
"Since recently announcing that we had received approval of the Cut and Fill Project Environmental and Social Impact Assessment ('ESIA'), we have now begun construction of the paste backfill plant. Construction of this part of Sasa's Cut and Fill Project therefore remains on schedule to be completed in H1 2023.
"In August, we made our final repayment of the $187 million debt which we secured to acquire Sasa less than five years ago. These repayments have been made while we remained consistently among the sector leading dividend payers, delivered value for all our stakeholders, and invested in our operations."
Health and Safety
There were no LTIs at either Kounrad or Sasa during Q3 2022.
Kounrad
Production and sales update
Kounrad Q3 2022 copper production of 4,067 tonnes brings output for the first nine months of 2022 to 10,685 tonnes. Copper sales during Q3 2022 were 4,093 tonnes, bringing the total for the first nine months of the year to 10,499 tonnes.
Sasa
Production and sales update
In Q3 2022, mined and processed ore were 200,379 tonnes and 200,087 tonnes respectively, bringing the total for the first nine months of 2022 to 602,587 tonnes of ore mined and 604,478 tonnes of ore processed. The average head grades for the quarter were 3.34% zinc and 3.67% lead, and for the first nine months of the year were 3.16% and 3.66% respectively.
Sasa produces a zinc concentrate and a separate lead concentrate. In Q3 2022, 11,364 tonnes of concentrate containing 50.6% zinc and 9,665 tonnes of concentrate containing 71.4% lead were produced. Total production for the first nine months of the year was 32,323 tonnes of zinc concentrate at an average grade of 50.2% and 29,172 tonnes of lead concentrate at an average grade of 71.0%.
Sasa typically receives from smelters approximately 84% of the value of its zinc in concentrate and approximately 95% of the value of its lead in concentrate. Accordingly, Q3 2022 payable production of zinc was 4,837 tonnes and of lead was 6,554 tonnes, bringing total payable production for the nine-month period to 13,625 tonnes of zinc and 19,690 tonnes of lead.
Given that deliveries from Sasa to the smelters occur on a regular basis, payable base metal in concentrate sales for the nine-month period were similar at 13,539 tonnes of zinc and 19,470 tonnes of lead.
During the first nine months of 2022, Sasa sold 237,636 ounces of payable silver to Osisko Gold Royalties, in accordance with its streaming agreement.
Units Q3 2022 9m 2022 9m 2021 Ore mined t 200,3 79 602,587 614,807 --------- --------- -------- -------- Plant feed t 200,08 7 604,478 626,906 --------- --------- -------- -------- Zinc grade % 3.34 3.16 3.19 --------- --------- -------- -------- Zinc recovery % 85.9 84.9 85.1 --------- --------- -------- -------- Lead grade % 3.67 3.66 3.54 --------- --------- -------- -------- Lead recovery % 94.0 93.7 93.4 --------- --------- -------- -------- Zinc concentrate t (dry) 11,364 32,323 34,003 --------- --------- -------- -------- * Grade % 50.6 50.2 50.1 --------- --------- -------- -------- * Contained zinc t 5,746 16,211 17,033 --------- --------- -------- -------- Lead concentrate t (dry) 9,665 29,172 28,856 --------- --------- -------- -------- * Grade % 71.4 71.0 71.9 --------- --------- -------- -------- * Contained lead t 6,899 20,726 22,300 --------- --------- -------- --------
Cut and Fill Project update
The permits required to begin construction of the paste backfill plant have been received and, in September, initial earthworks began. Construction of the paste backfill plant is on schedule to be completed in H1 2023, with the dry stack tailings component scheduled for completion during H2 2023. Development of the central decline continues to progress well, with 711 metres developed during the first nine months of 2022, and 1,218 metres in total.
For further information contact:
Central Asia Metals Tel: +44 (0) 20 7898 9001 Nigel Robinson CEO Gavin Ferrar CFO Louise Wrathall louise.wrathall@centralasiametals.com Director of Corporate Development Emma Chetwynd Stapylton emma.chetwyndstapylton@centralasiametals.com Investor Relations Manager Peel Hunt (Nominated Advisor and Tel: +44 (0) 20 7418 8900 Joint Broker) Ross Allister David McKeown BMO Capital Markets (Joint Broker) Tel: +44 (0) 20 7236 1010 Thomas Rider Pascal Lussier Duquette BlytheRay (PR Advisors) Tel: +44 (0) 20 7138 3204 Tim Blythe Megan Ray Rachael Brooks
Note to editors:
Central Asia Metals, an AIM-listed UK company based in London, owns 100% of the Kounrad SX-EW copper project in central Kazakhstan and 100% of the Sasa zinc-lead mine in North Macedonia.
For further information, please visit www.centralasiametals.com and follow CAML on Twitter at @CamlMetals and on LinkedIn at Central Asia Metals Plc.
This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
END
UPDFLFVRIRLDIIF
(END) Dow Jones Newswires
October 10, 2022 02:00 ET (06:00 GMT)
1 Year Central Asia Metal Chart |
1 Month Central Asia Metal Chart |
It looks like you are not logged in. Click the button below to log in and keep track of your recent history.
Support: +44 (0) 203 8794 460 | support@advfn.com
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions