
We could not find any results for:
Make sure your spelling is correct or try broadening your search.
Share Name | Share Symbol | Market | Type | Share ISIN | Share Description |
---|---|---|---|---|---|
Van Dieman | LSE:VDM | London | Ordinary Share | GB00B03HFG82 | ORD 1P |
Price Change | % Change | Share Price | Bid Price | Offer Price | High Price | Low Price | Open Price | Shares Traded | Last Trade | |
---|---|---|---|---|---|---|---|---|---|---|
0.00 | 0.00% | 0.875 | 0.00 | 00:00:00 |
Industry Sector | Turnover | Profit | EPS - Basic | PE Ratio | Market Cap |
---|---|---|---|---|---|
0 | 0 | N/A | 0 |
RNS Number:0489I Van Dieman Mines plc 20 November 2007 VAN DIEMAN MINES PLC (AIM: VDM) *Treatment Plant Site Works Commence at Scotia Mine *Treatment Plant in transit from the USA *Earthmoving equipment delivered to site Van Dieman Mines plc (AIM: VDM), the AIM listed mining company which is developing its 100% owned tin - sapphire mines in Tasmania, Australia, is pleased to announce that the primary treatment plant is currently in transit from the USA and despite continuing un-seasonal, inclement weather the Company's Gladstone staff continue to make excellent progress with pre-construction site works. The main access road to the Scotia treatment plant and workshop site and the new culvert crossing of the Pig & Whistle lagoon are all but completed save for minor drainage works and signage. An Aboriginal Heritage site inspection has been completed and the consultant has approved the area for all works listed under the DPEMP approval. The primary treatment plant, in transit from the USA, is scheduled to arrive in Tasmania during the week of November 19 2007. Work has commenced at the treatment plant and workshop site at the mine and arrangements are well advanced to complete pouring of the concrete footing pads in readiness for the treatment plant whose delivery to site is scheduled to commence at the end of November. The remaining units of the earthmoving fleet have been delivered to site. This will allow the crew to commence ore pre-stripping and dam wall construction during November/December while the treatment plant is being erected. From mid December, on an ongoing basis, ore will be stockpiled adjacent to the treatment plant site to provide feedstock for commissioning of the treatment plant in February, with full production expected to be achieved during March. Delays are being experienced with mains power connection. The power line easement has been cleared and the erection of power poles is scheduled for the end of November. The company is working closely with the supply authority, Aurora Energy, to expedite their stringing of overhead cable and installation of the supply sub-station in time for plant start up. 20 November 2007 Clive Trist, Managing Director, Van Dieman Mines, commented: "Despite un-seasonal weather in October, progress with site works at Scotia has kept to schedule and delays in the conduct and receipt of Aboriginal Heritage assessments have not affected works progress. Delivery of the remaining earthmoving units will allow the crew to commence ore pre-stripping and dam wall construction. We are working closely with Aurora to ensure connection to the power grid in time for start up. However we have all the stand-by generators on site and will, if necessary, utilise those for short term power supply. Orders have now been placed for the conveyors and while these will not be delivered until late March production is not expected to be delayed, as it will be achieved from ore stockpiled in the interim for that purpose." ENQUIRIES: VAN DIEMAN MINES plc Tel: +61 (0) 2 8908 5103 Clive Trist, Managing Director Email: clive.trist@vandiemanmines.com or admin@vandiemanmines.com GRANT THORNTON CORPORATE FINANCE Tel: +44 (0) 20 7383 5100 Fiona Owen FOX DAVIES CAPITAL LIMITED Tel: +44 (0) 20 7936 5230 Richard Hail, Corporate Finance BANKSIDE CONSULTANTS Tel: +44 (0) 20 7367 8888 Michael Padley / Louise Davis Background on Van Dieman (AIM: VDM) VDM is in the process of developing its alluvial tin, sapphire and accompanying mineral deposits in the northeast of Tasmania, Australia where it owns 15 exploration and retention licenses. Exploration and development planning consent is now complete for VDM's Scotia tin and sapphire mine which in full production will produce annually an estimated 700 tonnes of tin and 1.5 million carats of mine rough gem quality sapphire. A six-year contract is in place with tin smelter and refiner, Thaisarco, for the off-take at prevailing LME prices of the Company's entire tin concentrate output from the Scotia and Endurance mines expected to be 1,350 - 1,500 tonnes of contained tin per year. A joint venture marketing agreement is also in place for the marketing of the sapphire and spinel production NOTES: 1. DPEMP: the Development Plan and Environmental Management Plan required to be lodged and approved prior to commencement of mining activities The technical content of this announcement has been reviewed by a Director of Van Dieman Mines plc, Neil Kinnane, who has over 40 years experience in geology, exploration and mining and is a fellow of the Australasian Institute of Mining and Metallurgy (AusIMM), Chartered Practising Geologist, Member of Geological Society of America, Member of Geological Society of Australia, a recognized professional association. This information is provided by RNS The company news service from the London Stock Exchange END MSCILFSDLTLALID
1 Year Van Dieman Mines Chart |
1 Month Van Dieman Mines Chart |
It looks like you are not logged in. Click the button below to log in and keep track of your recent history.
Support: +44 (0) 203 8794 460 | support@advfn.com
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions