ADVFN Logo ADVFN

We could not find any results for:
Make sure your spelling is correct or try broadening your search.

Trending Now

Toplists

It looks like you aren't logged in.
Click the button below to log in and view your recent history.

Hot Features

Registration Strip Icon for default Register for Free to get streaming real-time quotes, interactive charts, live options flow, and more.

RRR Red Rock Resources Plc

0.0525
0.00 (0.00%)
03 May 2024 - Closed
Delayed by 15 minutes
Share Name Share Symbol Market Type Share ISIN Share Description
Red Rock Resources Plc LSE:RRR London Ordinary Share GB00BYWKBV38 ORD 0.01P
  Price Change % Change Share Price Bid Price Offer Price High Price Low Price Open Price Shares Traded Last Trade
  0.00 0.00% 0.0525 0.05 0.055 0.0525 0.0525 0.0525 133,145,131 08:00:00
Industry Sector Turnover Profit EPS - Basic PE Ratio Market Cap
Iron Ores 0 -2.67M -0.0011 -0.45 1.24M

Red Rock Resources plc Jupiter Mines - Update (9150Y)

07/01/2020 7:00am

UK Regulatory


Red Rock Resources (LSE:RRR)
Historical Stock Chart


From May 2019 to May 2024

Click Here for more Red Rock Resources Charts.

TIDMRRR

RNS Number : 9150Y

Red Rock Resources plc

07 January 2020

Red Rock Resources plc

("Red Rock " or the "Company")

Jupiter Mines - Update and Expansion

7 January 2020

Red Rock Resources Plc, the natural resource development company with interests in gold and battery metal and steel feed materials, announces that Jupiter Mines Limited ("Jupiter", ASX:JMS), an Australian public company in which Red Rock holds 17,024,914 shares (0.87%) and which owns 49.9% of the Tshipi Borwa manganese mine in South Africa, has released a statement, the text of which is set out below, to the Australian Stock Exchange:

"TSHIPI EXPANSION CONCEPT STUDY COMPLETED

Jupiter Mines Limited ("Jupiter" or "the Company") (ASX: JMS) is pleased to announce that the concept study into the expansion of the Tshipi Borwa Manganese Mine has been completed. A comprehensive feasibility study will commence shortly.

The feasibility study will be based on a production profile of 4.5 million tonnes (the "Base Case Scenario"), a 50% increase on the current 3 million tonne production level.

Production profiles in excess of the Base Case Scenario were explored as part of the concept study, however the infrastructure required is significantly less complex, will involve a shorter timeframe to implement, has a lower capital requirement, there is less reliance on road transport and the legal requirements are significantly more favourable from a timing perspective for the Base Case Scenario.

Some of the major constraints to go beyond the Base Case scenario include potential mining constraints, the lack of water in the area and logistical constraints in the medium term.

Infrastructural optionality will be considered for substantial production upside beyond the Base Case Scenario, to be leveraged upon in the future, should the constraints and market dynamics change.

Total capital expenditure required for the expansion is estimated to be R1.025 billion (+- 30% level of confidence). This expenditure provides for some of the infrastructure required for the production optionality mentioned above.

Subject to the completion of the feasibility study and commercial process (approximately 1 year), Tshipi would expect to reach steady state exports of 4.5 million tonne in 3 years, with an increase in manganese ore exports in year 2 and year 3, via a stepped approach".

Andrew Bell, Chairman, comments: "A potential 50% production increase over 3 years is one of a number of encouraging developments at Jupiter, which continues its drive to improved efficiencies and stringent cost control.

Jupiter has over the last 18 months exceeded its benchmark 70% dividend payout ratio, and the significant strengthening in the manganese price over the last two months testifies to the resilience of underlying demand.

The Company expects a continued growth over time in the level of contributions received from its holding in Jupiter."

 
 Note: 
 

The closing price of Jupiter shares in the market is A$0.29 per share as at 6(th) January 2020, and the A$0.04 per share (A$680,996 to Red Rock) interim dividend paid in November 2019 represents a six month yield of 13.8% at that price.

The full year dividend for Jupiter's year to 28 February 2019 was A$0.075, representing a 25.9% yield at the current price.

Jupiter 3(rd) quarter results to 30 November 2019 noted that sales were on track to meet the target for the year, and that cash stood at A$93m at the end of the quarter and after payment of the interim dividend.

Further details on Jupiter announcement may be found at www.jupitermines.com

For further information, please contact:

Andrew Bell 0207 747 9990 Chairman Red Rock Resources Plc

Scott Kaintz 0207 747 9990 Director Red Rock Resources Plc

   Roland Cornish/ Rosalind Hill Abrahams 0207 628 3396        NOMAD Beaumont Cornish Limited 

Tim Sohal 0203 700 2500 Broker Pello Capital Limited

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

END

UPDUNUARRWUARUR

(END) Dow Jones Newswires

January 07, 2020 02:00 ET (07:00 GMT)