ADVFN Logo ADVFN

We could not find any results for:
Make sure your spelling is correct or try broadening your search.

Trending Now

Toplists

It looks like you aren't logged in.
Click the button below to log in and view your recent history.

Hot Features

Registration Strip Icon for charts Register for streaming realtime charts, analysis tools, and prices.

0HN3 Bhp Billiton Ltd

51.49
0.00 (0.00%)
Last Updated: 00:00:00
Delayed by 15 minutes
Share Name Share Symbol Market Type Share ISIN Share Description
Bhp Billiton Ltd LSE:0HN3 London Ordinary Share BHP BILLITON ADR REPTG 2 ORD SHS
  Price Change % Change Share Price Bid Price Offer Price High Price Low Price Open Price Shares Traded Last Trade
  0.00 0.00% 51.49 1 00:00:00
Industry Sector Turnover Profit EPS - Basic PE Ratio Market Cap
Crude Petroleum & Natural Gs 56.94B 7.9B 1.5600 26.83 260.66B

BHP Group Limited BHP approves investment in Jansen Stage 2 (8405R)

31/10/2023 7:42am

UK Regulatory


Bhp Billiton (LSE:0HN3)
Historical Stock Chart


From Dec 2022 to Dec 2024

Click Here for more Bhp Billiton Charts.

TIDMBHP

RNS Number : 8405R

BHP Group Limited

31 October 2023

Exchange release

31 October 2023

BHP approves US$4.9 billion investment in stage two of Jansen potash project

BHP has approved an investment of US$4.9 billion (C$6.4 billion) for stage two of the Jansen potash project (Jansen Stage 2) in Saskatchewan, Canada.

This follows BHP's approval of US$5.7 billion (C$7.5 billion) for stage one of the Jansen potash project (Jansen Stage 1) in August 2021 and a pre-Jansen Stage 1 investment of US$4.5 billion (C$4.9 billion).

BHP Chief Executive Officer, Mike Henry said:

"This is an important milestone that underscores our confidence in potash and marks the next phase of the company's growth in Canada. We believe Jansen will deliver long-term value for shareholders and the local community, and will position BHP as one of the leaders in the global potash industry.

The stage two investment advances BHP's strategy to increase its exposure to commodities positively leveraged to the global megatrends of population growth, urbanisation, rising living standards and decarbonisation. Potash, used in fertilisers, will be essential for food security and more sustainable farming.

Today's additional investment will transform Jansen into one of the world's largest potash mines, doubling production capacity to approximately 8.5 million tonnes per annum (Mtpa)(1) .

We are advancing our sustainability and economic development priorities for Jansen and we are pleased with the progress of our ongoing work with the Governments of Canada and Saskatchewan, as well as local and Indigenous communities on shared solutions."

Jansen Stage 1 is 32% complete and progressing in line with its schedule. First production from Jansen Stage 1 is expected to be delivered in late CY2026. Construction of Jansen Stage 2 is anticipated to take approximately six years, and is expected to deliver first production in FY2029, followed by a ramp up period of three years.

Jansen Stage 2 is expected to deliver approximately 4.36 Mtpa of production at a capital intensity of approximately US$1,050/t, lower than Jansen Stage 1, due to the leveraging of existing and planned infrastructure(2) . In October 2022, BHP approved an initial funding commitment of US$188 million to procure long lead equipment and commence process plant foundation works. The additional US$4.9 billion investment for Jansen Stage 2 will be used for the development of additional mining districts, completion of the second shaft hoist infrastructure to handle higher mining volumes, expansion of processing facilities and the addition of more rail cars.

Westshore Terminals, in Delta, British Columbia, remains BHP's main port facility to ship potash from Jansen to customers. The Jansen Stage 2 investment includes funding to increase storage facilities at the port. BHP will not be initiating a formal capacity extension for the Westshore port terminal at this time and will evaluate closer to Jansen Stage 2 reaching first production.

Jansen has been designed with a focus on social value and sustainability and is expected to have approximately 50% less operational (Scopes 1 and 2) greenhouse gas emissions per tonne of product and use up to 60% less fresh water when compared to the average potash mine in Saskatchewan. Indigenous employee representation at Jansen has increased to approximately 9% with a target to increase Indigenous employee representation at Jansen to 20%. Jansen aspires to maintain a gender balanced workforce.

Jansen Stage 2 was evaluated utilising BHP's Capital Allocation Framework and at consensus prices has an internal rate of return of 15% to 18% and an expected payback period of approximately six years from first production(3) . Underlying EBITDA margins for Jansen Stage 1 and Stage 2 of approximately 65% to 70% are expected due to a low-cost position of US$105 to US$120/t(4) .

Transitioning to Jansen Stage 2 during the construction period of Jansen Stage 1 is expected to bring a number of operational benefits. These include leveraging the experience of the integrated Jansen project team, continued use of existing contractors, reduced overheads and savings on mobilisation and demobilisation costs. Potential synergies of US$0.3 billion have been embedded into Jansen Stage 2's economics.

Longer term, Jansen has the potential for two additional expansions to reach an ultimate production capacity of 16 to 17 Mtpa (subject to studies and approvals).

The Jansen Mineral Resources and Jansen Ore Reserves as at 30 September 2023 and the report issued in support of the declaration of Mineral Resources and Ore Reserves that accompanies the investment in the Jansen Stage 2 project can be accessed via BHP's website at https://www.bhp.com and has been submitted to the FCA National Storage Mechanism and will shortly be available for inspection at: https://data.fca.org.uk/#/nsm/nationalstoragemechanism

Footnotes

1. Jansen Stage 1 production capacity was reduced by 0.2Mt by deferring the investment in the recovery circuit in order to enable better capital efficiency outcomes and capture economies of scale by having a combined circuit for Jansen Stage 1 and Stage 2.

   2.   Expected capital intensity for Jansen Stage 2, US$/product tonne, Real 1 July 2023. 

3. Price assumptions reflect the average of Argus and CRU prices. Jansen Stage 2 internal rate of return range is post-tax, nominal and reflects Argus and CRU prices (Average 2029-2039: US$369/t Argus and US$466/t CRU). The internal rate of return is the expected internal rate of return based on incremental Jansen Stage 2 cashflow across approximately 50-year mine life.

4. Operational expenditure includes costs relating to the Jansen mine and port and rail costs, excludes carbon tax, Real 1 July 2023.

Authorised for release by Stefanie Wilkinson, Group Company Secretary.

 
 Contacts 
----------------------------------------------------------------- 
 Media                             Investor Relations 
  media.relations@bhp.com           investor.relations@bhp.com 
 Australia and Asia                Australia and Asia 
  Gabrielle Notley                  John-Paul Santamaria 
  +61 411 071 715                   +61 499 006 018 
 Europe, Middle East and Africa    Europe, Middle East and Africa 
  Neil Burrows                      James Bell 
  +44 7786 661 683                  +44 7961 636 432 
 Americas                          Americas 
  Megan Hjulfors                    Monica Nettleton 
  +1 (403) 605-2314                 +1 (416) 518-6293 
 BHP Group Limited 
  ABN 49 004 028 077 
  LEI WZE1WSENV6JSZFK0JC28 
  Registered in Australia 
  Level 18, 171 Collins Street 
  Melbourne 
  Victoria 3000 Australia 
  Tel: +61 1300 55 4757 Fax: +61 
  3 9609 3015 
  BHP Group is headquartered in 
  Australia 
 
  bhp.com 
 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.

END

UPDWPGBWUUPWUMG

(END) Dow Jones Newswires

October 31, 2023 03:42 ET (07:42 GMT)

1 Year Bhp Billiton Chart

1 Year Bhp Billiton Chart

1 Month Bhp Billiton Chart

1 Month Bhp Billiton Chart

Your Recent History

Delayed Upgrade Clock