Recent Highlights
Corporate
Operations
Financial
Commenting on the results, Michael Staresinic, President and Chief Executive Officer of TVC stated, "This past quarter showed a marked improvement with our flagship project, the construction and development of our underground mine, Papomono. Since the renegotiation of this contract in August, the contractor has performed much better than we previously experienced with multi 200-meter month advancements. We are approaching 90% completion of the required meters to begin producing and expect our first caving of ore to begin in January 2022."
"As we continued our assessment of Papomono during the quarter given its paramount importance to the Company, it was concluded that to further ensure its successful ramp-up during 2022 and maximize its economic benefit, we decided to bring forward sustaining capital expenditures originally planned for later years to 2022. This decision came at a time when our open pit operations at Don Gabriel continued its underperformance delivering less ore at a lower grade that will lead to cathode production at the lower end of our 2021 revised guidance. The Company's original plan for 2021 included reinvesting the cash flows delivered by Don Gabriel to fund development of Papomono but unfortunately, this has not happened and we foresaw near-term capital stresses to the business. Our announced strategic review in October was, in part, to help address this and quickly led to a required near-term financing raising gross proceeds of C$18.2 million."
"With this financing we eliminated the short-term liquidity issue that was on the horizon allowing us to continue completing Papomono in January 2022 and increasing production in 2022. The completion of Papomono continues to be our focus and any deviation or delay would be value destructive to stakeholders. Our senior lenders agreed with us and as a condition of the financing, continued their strong partnership by agreeing to forbear on the debt repayments due in the first three quarters of 2022 while we together continue to renegotiate new repayment terms of the senior debt facility."
"This new capital also allows the strategic review process to move forward without undue pressure. This new capital secures a better future for the MTV project and assists the strategic review process underway which ultimately we believe will increase shareholder value."
"Our exploration program continues and with over 46,000 hectares available to explore with highly prospective exploration targets including the 100 outcrop copper occurrences identified and 170,000 meters of diamond drilling performed by previous owners, we expect to provide preliminary results from this campaign in the first half of 2022. We hope this is the beginning of a multi-year exploration program and expansion of the copper resources contained in our land tenure."
"We are very proud of our health and safety record with every health and safety statistic reporting below the country averages and specific to COVID-19, our initiated on-site vaccination program has resulted in approximately 94% of the workforce receiving both doses of the vaccine and nearly 100% of the workforce has opted to participate. We have already begun a booster shot program to supplement this."
Much has been accomplished by the team in Chile during 2021 through a restart of mining operations all complicated by the complexities of COVID-19. The copper price has remained above $4 per pound for almost all of 2021 and we see this level of support continuing. And the longer this trend continues, the more capital and attention the industry will attract. Three Valley Copper will not be overlooked. TVC is uniquely positioned among junior copper companies to take advantage of this coming cycle - fully built infrastructure, producing operations with defined deposits and, a rich land package in a very good neighborhood."
Operational Results Summary
Three months ended | Nine months ended | |||||||||||
Operating information | Sept. 30, 2021 | Sept. 30, 2020 | Sept. 30, 2021 | Sept. 30, 2020 | ||||||||
Copper (MTV Operations) | ||||||||||||
Total ore mined (thousands of tonnes) | 178 | 49 | 550 | 351 | ||||||||
Grade of ore mined (% Cu) | 0.52 | % | 0.88 | % | 0.54 | % | 0.86 | % | ||||
Total waste mined (thousands of tonnes) | 739 | 118 | 1,358 | 853 | ||||||||
Ore Processed (thousands of tonnes) | 231 | 90 | 680 | 474 | ||||||||
Cu Production (tonnes) | 1,138 | 1,077 | 3,073 | 3,789 | ||||||||
Cu Production (thousands of pounds) | 2,509 | 2,374 | 6,775 | 8,353 | ||||||||
Change in inventory ($000s) | $ | 3,563 | (11 | ) | $ | 10,427 | (4,421 | ) | ||||
Cash cost of copper produced 1 (USD per pound) | $ | 3.40 | $ | 2.44 | $ | 3.49 | $ | 2.75 | ||||
Realized copper price 2 (USD per pound) | $ | 3.58 | $ | 2.82 | $ | 3.48 | $ | 2.46 |
1 Cash cost per pound of copper produced includes all costs absorbed into inventory including inventory write-downs less non-cash items such as depreciation and non-site charges. It is a non-IFRS performance measure. Refer to Non-IFRS Performance Measures.
2 Realized copper price is a non-IFRS performance measures. Refer to Non-IFRS Performance Measures.
Ore Production
Construction and Development of Papomono Masivo
Exploration
COVID-19
Financial Results Summary
Three months ended | Nine months ended | |||||||||||
Financial information (in thousands) | Sept. 30, 2021 | Sept. 30, 2020 | Sept. 30, 2021 | Sept. 30, 2020 | ||||||||
Revenue | $ | 8,362 | $ | 5,610 | $ | 22,873 | $ | 17,700 | ||||
Gross loss | $ | 881 | $ | 552 | $ | 3,070 | $ | 9,546 | ||||
Net loss from continuing operations | $ | 1,474 | $ | 335 | $ | 9,407 | $ | 21,167 | ||||
Net loss from discontinued operations | $ | — | $ | — | $ | — | $ | 2,241 | ||||
Net loss for the period | $ | 1,474 | $ | 335 | $ | 9,407 | $ | 23,408 | ||||
Net loss per share attributable to owners of the Company | $ | 0.02 | $ | 0.01 | $ | 0.16 | $ | 0.48 | ||||
EBITDA from continuing operations 1 | $ | 2,254 | $ | 1,873 | $ | 1,347 | $ | (12,695 | ) | |||
Adjusted EBITDA from continuing operations 1 | $ | (392 | ) | $ | (926 | ) | $ | 440 | $ | (4,529 | ) | |
Gain (loss) on portfolio investments | $ | — | $ | 1,038 | $ | 107 | $ | (1,294 | ) | |||
Impairment of non-current assets | $ | — | $ | — | $ | — | $ | (7,628 | ) | |||
Reversal (write-down) of inventory | $ | — | $ | 665 | $ | (2,474 | ) | $ | (3,441 | ) | ||
Gain on modification of debt | $ | — | $ | 3,487 | $ | — | $ | 3,487 | ||||
Cash used in operating activities before working capital changes | $ | (1,229 | ) | $ | (1,097 | ) | $ | (103 | ) | $ | (4,412 | ) |
1 Refer to Non-IFRS Performance Measures
Financial Results
Revenues of $8.4 million for the three months ended September 30, 2021 were generated predominantly from the sale of copper cathodes. Finished goods inventory at September 30, 2021 was approximately $2.9 million. Copper cathodes sold for the three months ended September 30, 2021 of 1,060 tonnes was higher than the comparative quarter in 2020 of 858 tonnes with their respective revenues based on an average realized copper price of $3.58 per pound and $2.82 per pound.
The Company reported a gross loss of $0.9 million for the three months ended September 30, 2021, mainly due to higher operating costs resulting from lower-than-expected grades of the ore mined from Don Gabriel. A reversal of previous write-down of inventory of $0.7 million that was recorded as a decrease to cost of sales offset the gross loss of $0.6 million for the comparable quarter.
Revenues of $22.9 million for the nine months ended September 30, 2021 were generated predominantly from the sale of copper cathodes. Copper cathodes sold for the nine months ended September 30, 2021 of 2,975 tonnes was lower than the comparative period in 2020 of 3,068 tonnes. The decrease in tonnes of the copper cathodes sold in 2021 was more than offset by the average realized copper price of $3.48 per pound, which increased by 41% from $2.46 per pound in the nine months ended September 30, 2020.
The Company reported a gross loss of $3.1 million for the nine months ended September 30, 2021 that includes a write-down of inventory, net of reversals of $2.5 million that is recorded as an increase to cost of sales. Included in the gross loss of $9.5 million for the comparable period, is a write-down of inventory, net of reversals of $3.4 million that is recorded as an increase to cost of sales.
In accordance with the Offtake with AAML, MTV sold 46% of its copper cathode production at $2.89 per pound for the three months ended September 30, 2021. This percentage is higher than the expected 40% as copper cathode production was lower during the nine months ended September 30, 2021 than was anticipated when the fixed priced portion of the contract was entered into.
Effective August 1, 2021 MTV entered into an amendment to the Offtake specific to the fixed prices sales component with AAML. Under the terms of the amendment, the remaining monthly deliveries of copper cathodes due under the fixed price portion of the Offtake are deferred until May 1, 2022 and all sales of copper cathodes commencing August 1, 2021 until April 30, 2022 will be sold at the prevailing spot price for copper cathode, less a nominal amount. The remaining 12 months of contracted delivery amounts of the fixed price portion of the contract will resume on May 1, 2022 at the previous agreed fixed price of $2.89 per pound.
The increasing copper price together with MTV's obligation to sell a set amount of its production at $2.89 per pound affected the economics of purchasing ore from third-party small miners at market until July 31, 2021, but thereafter, the amendment to the Offtake significantly benefited ore supply from third-party small miners. The amendment allowed the Company to purchase ore from third-party miners at more competitive rates driving a progressive increase in ore supply up to October 2021, when MTV purchased over 21,000 tonnes of ore from third-party miners, which was 17% above the expected 18,000 tonnes.
The Company's general and administrative expense for the three and nine months ended September 30, 2021 was $1.3 million and $3.2 million compared to $0.8 million and $3.2 million, respectively, in the comparative periods, showing an increase in marketing expenses in the three months ended September 30, 2021, compared to the same period of 2020.
Finance expenses for the three and nine months ended September 30, 2021 totaled $2.4 million and $6.8 million compared to $1.2 million and $4.5 million, respectively, in the comparative periods, as the average balance of the Company's long-term debt grew. Given the current grace period achieved for the long-term debt under MTV's restructuring in 2020, cash interest payments made during the three and nine months ended September 30, 2021 amounted to $1.1 million and $1.8 million, respectively.
The Company reported a quarterly net loss attributable to owners of the Company of $1.3 million or $0.02 per share. Adjusted EBITDA (see Non-IFRS Financial Measures) from continuing operations for the three months ended September 30, 2021 was negative $0.4 million or $0.01 per share. For the comparable quarter in 2020, the Company reported a net loss attributable to owners of the Company of $0.3 million or $0.01 per share and Adjusted EBITDA from continuing operations of negative $0.9 million or $0.03 per share.
In the first three quarters of 2021, the Company reported a net loss attributable to owners of the Company of $7.6 million or $0.16 per share. Adjusted EBITDA (see Non-IFRS Financial Measures) from continuing operations for the nine months ended September 30, 2021 was $0.4 million or $0.01 per share. For the comparable quarters of 2020, the Company reported a net loss attributable to owners of the Company of $16.2 million or $0.48 per share and Adjusted EBITDA from continuing operations of negative $4.5 million or $0.14 per share.
In the first three quarters of 2021, cash used in operating activities was $9.8 million (cash used of $0.1 million before changes in non-cash components of working capital), compared with 2020 when cash used in operating activities was $2.4 million (cash used of $4.4 million before changes in non-cash components of working capital).
Cash Position, Working Capital and Net Debt
Cash and cash equivalents decreased to $6.7 million at September 30, 2021 from $12.0 million at December 31, 2020 mainly due to $9.8 million used in operating activities, $7.7 million of disbursed capital expenditures mainly related to the construction and development of Papomono Masivo and $1.8 million of interest payments; all partially offset by $8.3 million of net proceeds from the April 2021 bought deal financing, $6.2 million of net proceeds from loans and borrowings and $0.4 million of net proceeds from the exercise of warrants.
The Company has working capital (see Non-IFRS Financial Measures) of $3.1 million at September 30, 2021 and approximately $27.5 million as at the date hereof. Cash position as at the date hereof is approximately $17.8 million.
The Company is substantially leveraged. The Company's net debt (see Non-IFRS Financial Measures) at September 30, 2021 was $67.1 million. The Company's debt position continues to increase as it capitalizes interest and remains in a grace period for the majority of its debt (see the Undertaking in Recent Highlights previously).
Health and Safety
For the three months ended September 30, 2021, there was no Lost-Time Incident. MTV's annual injury frequency index continues to remain below the average of the mining industry in Chile. The Company and MTV devote considerable time and effort to ensure that workers and contractors return safely to their families after each shift. Safety statistics are monitored and compared to the country and peer averages, and MTV pro-actively engages in education and assessment to achieve a goal of zero lost-time incidents.
Community and Environment
MTV continues to actively work with local communities and stakeholders and for the three months ended September 30, 2021, the MTV Foundation continued the funding of projects agreed to by the MTV Foundation board, which is largely composed of community representatives to help MTV understand the true needs of its neighbors, such as starting an eco-friendly cooperative at a local school. MTV’s ore purchase program also ensures support from local miners, buying ore from over 26 providers and supporting the development of over 300 small-scale miners through local mining unions.
Ongoing Arbitration
As previously disclosed, the Company is involved in an arbitration proceeding with the Minority Shareholder of MTV. The arbitration proceeding is continuing and no further material developments have occurred. The Company remains confident in its position and is monitoring the arbitration proceeding and its process closely.
Qualified Persons
The scientific and technical content contained in this news release is taken from the technical report (the "Technical Report") entitled “Minera Tres Valles Copper Project, Salamanca, Coquimbo Region, Chile NI 43-101 Technical Report” prepared by Dr Antonio Luraschi, RM CMC, Manager of Metallurgic Development and Senior Financial Analyst, Wood, Mr Alfonso Ovalle, RM CMC, Mining Engineer, Wood, Mr Michael G. Hester, FAusIMM, Vice President and Principal Mining Engineer, Independent Mining Consultants, Inc., Mr Enrique Quiroga, RM CMC, Mining Engineer, Q&Q Ltda, Mr Gabriel Vera, RM CMC, Metallurgical Process Consultant, GVMetallurgy, and Mr Sergio Alvarado, RM CMC, Consultant Geologist, General Manager and Partner, Geoinvestment Sergio Alvarado Casas E.I.R.L. all of whom were independent qualified persons as defined by NI 43-101 at the time the Technical Report was prepared. The Technical Report was filed by TVC on SEDAR (www.sedar.com) on December 14, 2018 and subsequently amended and restated on May 27, 2021. Readers are encouraged to read the Technical Report in its entirety except for certain sections withdrawn by the Company in relation to disclosure regarding the Preliminary Economic Assessment appearing in the Technical Report (see press release dated April 12, 2021).
About Three Valley Copper Corp.
TVC, headquartered in Toronto, Ontario, Canada is focused on growing copper production from, and further exploration of, its primary asset, Minera Tres Valles SpA. Located in Salamanca, Chile, MTV is 91.1% owned by the Company and MTV's main assets are the Minera Tres Valles mining complex and its 46,000 hectares of exploratory lands. For more information about TVC, please visit www.threevalleycopper.com.
Non-IFRS Performance Measures
"Cash costs", "EBITDA", "Adjusted EBITDA", "Realized copper price", "Working Capital" and "Net Debt" are non-IFRS performance measures. These non-IFRS performance measures do not have a standardized meaning prescribed by IFRS. These measures may differ from those used by, and may not be comparable to such measures as reported by, other issuers. The Company believes that these measures are commonly used by certain investors, in conjunction with conventional IFRS measures, to enhance their understanding of the Company’s performance. For further information and a detailed reconciliation of each non-IFRS measure used in this press release to the most directly comparable IFRS measure, please refer to the Company’s MD&A and accompanying TVC financial statements filed on SEDAR at www.sedar.com.
Cautionary Statement Regarding Forward-Looking Information
Certain statements in this news release, contain forward-looking information (collectively referred to herein as the "Forward-Looking Statements") within the meaning of applicable Canadian securities laws. The use of any of the words "expect", "anticipate", "continue", "estimate", "may", "will", "project", "should", "believe", "plans", "intends" and similar expressions are intended to identify Forward-Looking Statements. In particular, but without limiting the foregoing, this news release contains Forward-Looking Statements pertaining to: future outcomes and expectations related to MTV's ongoing operations, impacts of a favorable copper price environment in the future; expectations regarding the costs and timing of constructing Papomono Masivo including impacts of the labour market in Chile; impacts of COVID-19 and the Company’s and MTV’s precautions to manage and mitigate same; expectations regarding production following construction and ability and timing of generation of cash flow; the sale of copper at prevailing market prices under the offtake agreement improving cash flow; ongoing geopolitical risks in Chile; expectations regarding the Company's revised 2021 guidance; the long-term mine plan at Papomono Masivo and the timing in respect of production growth therefrom; future block caving efforts and the expected benefits therefrom and timing thereof; expectations regarding exploration, the cost, timing and success of such initiatives; and MTV's labour and health and safety initiatives and expectations.
Although TVC believes that the Forward-Looking Statements are reasonable, they are not guarantees of future results, performance or achievements. A number of factors or assumptions have been used to develop the Forward-Looking Statements, including: there being no additional significant disruptions affecting the development and operation of MTV; the availability of certain consumables (including water) and services and the prices for power and other key supplies being approximately consistent with assumptions in the Technical Report; labour and materials costs being approximately consistent with assumptions in the Technical Report; fixed operating costs being approximately consistent with assumptions in the Technical Report; permitting and arrangements with stakeholders being consistent with current expectations as outlined in the Technical Report; certain tax rates, including the allocation of certain tax attributes, being applicable to MTV; the availability of financing for the Company's and MTV’s planned operations and development activities; assumptions made in mineral resource and mineral reserve estimates and the financial analysis based on these estimates, including (as applicable), but not limited to, geological interpretation, grades, commodity price assumptions, metallurgical performance, extraction and mining recovery rates, hydrological and hydrogeological assumptions, capital and operating cost estimates, and general marketing, political, business and economic conditions, the continued availability of quality management, critical accounting estimates, all terms of the restructuring agreement and facility agreement to which MTV and the Company are parties will be satisfied in the future including no events of default, existing water supply will continue, supplemental water availability will continue, the geopolitical risk of Chile will remain stable, including risks related to labour disputes, the construction and expansion of mining operations including the Papomono Masivo incline block caving underground mining project, as well as the timing thereof and production therefrom; the timing of production and results for the recently restarted Don Gabriel mine; and expected timelines for drawdown and repayment of indebtedness of MTV.
Actual results, performance or achievements could vary materially from those expressed or implied by the Forward-Looking Statements should assumptions underlying the Forward-Looking Statements prove incorrect or should one or more risks or other factors materialize, including: (i) possible variations in grade or recovery rates; (ii) copper price fluctuations and uncertainties; (iii) delays in obtaining governmental approvals or financing; (iv) risks associated with the mining industry in general (e.g., operational risks in development, exploration and production; delays or changes in plans with respect to exploration or development projects or capital expenditures; the uncertainty of estimates and projections relating to mineral reserves, production, costs and expenses; and labour, health, safety and environmental risks) and risks associated with the other portfolio companies' industries in general; (v) performance of the counterparty to the ENAMI Contract; (vi) risks associated with investments in emerging markets; (vii) general economic, market and business conditions; (viii) market volatility that would affect the ability to enter or exit investments; (ix) failure to secure additional financing in the future on acceptable terms to the Company, if at all; (x) commodity price and foreign exchange fluctuations and uncertainties; (xi) risks associated with catastrophic events, manmade disasters, terrorist attacks, wars and other conflicts, or an outbreak of a public health pandemic or other public health crises, including COVID-19; (xii) being inconsistent those risks disclosed under the heading "Risk Management" in TVC’s Management’s Discussion and Analysis for the period ended December 31, 2020; and (xiii) being inconsistent with current expectations including, without limitation, the impact of any political tensions and uncertainty in Chile, or actions taken by any local or national government, including but not limited to amendments to mining laws and regulatory actions, (xiv) the impact and probability of operational, geological and environmental risks at MTV being inconsistent with current expectations (xiv) outcomes and potential benefits of the strategic review process; intended expenditures of the uses of proceeds from the Bought Deal Financing and benefits received from said expenditures; the progress and outcome of negotiations with the Lenders to restructure the Company's debt under the Amended Facility; timing and expectations related to arbitration with the Company's minority shareholder, (xvi) those risks disclosed under the heading "Risk Factors" or incorporated by reference into TVC’s Annual Information Form dated March 3, 2021. The Forward-Looking Statements speak only as of the date hereof, unless otherwise specifically noted, and SRHI does not assume any obligation to publicly update any Forward-Looking Statements, whether as a result of new information, future events or otherwise, except as may be expressly required by applicable Canadian securities laws.
Cautionary Note to United States Investors Concerning Estimates of measured, indicated and inferred mineral resources
This news release may use the terms "measured", "indicated" and "inferred" mineral resources. Historically, while such terms were recognized and required by Canadian regulations, they were not recognized by the United States Securities and Exchange Commission (the “SEC”). The SEC has adopted amendments to its disclosure rules to modernize the mineral property disclosure requirements for issuers whose securities are registered with the SEC under the Securities and Exchange Act of 1934, as amended (the “Exchange Act”). These amendments became effective February 25, 2019 (the “SEC Modernization Rules”) with compliance required for the first fiscal year beginning on or after January 1, 2021. The SEC Modernization Rules replace the historical property disclosure requirements for mining registrants that were included in SEC Industry Guide 7, which will be rescinded from and after the required compliance date of the SEC Modernization Rules. As a result of the adoption of the SEC Modernization Rules, the SEC now recognizes estimates of “measured”, “indicated” and “inferred” mineral resources. In addition, the SEC has amended its definitions of “proven mineral reserves” and “probable mineral reserves” to be substantially similar to the corresponding Canadian Institute of Mining, Metallurgy and Petroleum definitions, as required by NI 43-101. Investors are cautioned that "Inferred mineral resources" have a great amount of uncertainty as to their existence, and as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or other economic studies. United States investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral reserves. United States investors are also cautioned not to assume that all or any part of an inferred mineral resource exists or is economically or legally mineable.
For further information:
Michael StaresinicPresident and Chief Executive OfficerT: (416) 943-7107E: mstaresinic@threevalleycopper.com
Renmark Financial Communications Inc.Joshua Lavers: jlavers@renmarkfinancial.com T: (416) 644-2020 or (212) 812-7680www.renmarkfinancial.com
Source: Three Valley Copper Corp.
1 Year Three Valley Copper Chart |
1 Month Three Valley Copper Chart |
It looks like you are not logged in. Click the button below to log in and keep track of your recent history.
Support: +44 (0) 203 8794 460 | support@advfn.com
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions