R Romarco Minerals Inc.

0.00
0.00 (0.00%)
Share Name Share Symbol Market Type
Romarco Minerals Inc. TSXV:R TSX Venture Common Stock
  Price Change % Change Share Price Bid Price Offer Price High Price Low Price Open Price Shares Traded Last Trade
  0.00 0.00% 0 -

Romarco-More Drilling Planned at Haile

05/02/2009 2:42pm

Marketwired


Romarco Minerals Inc. (TSXV:R)
Historical Stock Chart


From May 2019 to May 2024

Click Here for more Romarco Minerals Inc. Charts.

ROMARCO MINERALS INC. (TSX VENTURE: R) (the "Company") is pleased to announce its 2009 exploration plans and project development schedule for the Haile Gold Mine in South Carolina.

Exploration Plans

Romarco's initial plan was to drill 22,000 meters in 2009, nearly three times the drilling completed in 2008. However, now the Company is making plans to increase this year's program to 85,000 meters through the addition of a second rig and double shifts on each rig. Two-thirds of the drilling this year will be step-out exploration holes in known mineralized areas adjacent to the deposits. The balance of the drilling will be in-fill to convert measured and indicated resources into reserves.

To date, the Company has focused its exploration in the highly prospective North Resource Area which remains open in three directions and at depth. Feasibility study related mine design has also shown substantial potential targets exist on other areas of the property. These targets are adjacent to the South Pit (to the north and west of the current reserve), the Snake Pit on the east side of the property, mineralized potential at depth, as well as targets identified on the newly acquired land parcels along strike. The current land package hosts 3.2 kilometers of strike length.

A total of 52 holes were drilled in 2008 with assays received and reported for 45 holes to date. Of those 45 holes:

87% returned more than 3 g/t gold over the mineralized interval

94% returned more than 1 g/t gold over the mineralized interval

60% returned more than 30 meters of 2.5 g/t gold

25% returned more than 30 meters of 4.0 g/t gold

Development Plans

Romarco's recently announced Feasibility Study (see press release dated February 3, 2009) demonstrated the robust economics of Haile. Optimization of the project will occur over the next quarter after which detailed engineering of Phase 1 (7000 tons per day) shall commence. The success of last years drilling combined with the team's optimism about future exploration at Haile has prompted the consideration of a Phase 2 (additional 7,000 tons per day) process facility.

The development plan is to commence detailed engineering concurrently with securing the remaining permits. Coincident with obtaining permits, plant construction will start early in the second quarter of 2010 with project completion targeted for mid-year 2011. Even after gold production begins at Haile, the Company anticipates exploration drilling to continue for several years.

The Feasibility Study was based on a proven reserve of 7.3 million tonnes averaging 2.52 g/t gold and a probable reserve of 10.5 million tonnes averaging 2.05 g/t gold. The combined proven and probable reserve as of October 2008 is 1.3 million ounces of gold at 2.24 g/t. The corresponding gold resource that formed the basis for the reserve and feasibility study is detailed in the table below. A cutoff grade of 0.514 g/t gold was used for resource. The measured and indicated resource increased by 2.22 million tonnes from the last reported estimate (see press release dated Sept. 4, 2008) due to inclusion of assays from six additional drill holes. This resulted in an increase in the proven and probable reserve as well as an increase in grade from 1.97 g/t to 2.24 g/t.

A revised reserve and resource estimate will be available in March 2009 - this update will include drill results received from October 2008 through January 2009.


Haile Gold Mine Project
Lancaster County S.C.
Estimated Minable Reserve

------------------------------------------------------------------------
                                                               Contained
                                        Tonnes    Gold Grade        Gold
Proven Reserve                           (000s)         (g/t)    (000 oz)
------------------------------------------------------------------------
0.015 oz/t (0.343 g/t)                   8,331          2.28         610
------------------------------------------------------------------------
0.020 oz/t (0.514 g/t)                   7,282          2.52         590
------------------------------------------------------------------------

Probable Reserve
------------------------------------------------------------------------
0.015 oz/t (0.343 g/t)                  12,290          1.84         729
------------------------------------------------------------------------
0.020 oz/t (0.514 g/t)                  10,529          2.05         695
------------------------------------------------------------------------

Proven and Probable Reserve
------------------------------------------------------------------------
0.015 oz/t (0.343 g/t)                  20,621          2.02       1,338
------------------------------------------------------------------------
0.020 oz/t (0.514 g/t)                  17,811          2.24       1,285
------------------------------------------------------------------------

Inferred Resource within Designed Pit
------------------------------------------------------------------------
0.015 oz/t (0.343 g/t)                   4,883          1.36         214
------------------------------------------------------------------------
0.020 oz/t (0.514 g/t)                   3,912          1.55         195
------------------------------------------------------------------------



Haile Gold Mine Project
Lancaster County S.C.
Estimated Mineral Resource

------------------------------------------------------------
Measured               Tonnes     Gold Grade       Contained
Cutoff (oz/ton)        (000's)         (gm/t)   Gold (000 oz)
------------------------------------------------------------
0.010                  12,588          1.737             703
------------------------------------------------------------
0.015                   9,973          2.082             668
------------------------------------------------------------
0.020                   8,376          2.367             637
------------------------------------------------------------
Indicated
Cutoff (oz/ton)
------------------------------------------------------------
0.010                  26,158          1.216           1,022
------------------------------------------------------------
0.015                  18,616          1.537             920
------------------------------------------------------------
0.020                  13,814          1.866             829
------------------------------------------------------------
Meas + Indic
Cutoff (oz/ton)
------------------------------------------------------------
0.010                  38,746          1.385           1,725
------------------------------------------------------------
0.015                  28,588          1.727           1,588
------------------------------------------------------------
0.020                  22,191          2.055           1,466
------------------------------------------------------------
Inferred
Cutoff (oz/ton)
------------------------------------------------------------
0.010                  27,547          0.858             760
------------------------------------------------------------
0.015                  16,877          1.136             616
------------------------------------------------------------
0.020                  11,232          1.409             509
------------------------------------------------------------

The Company will be filing an NI 43-101 technical report covering the Feasibility Study on SEDAR in the very near future. Please visit the Company's website for the latest information.

This press release has been reviewed and approved for release by Ken Brunk, P.E. (COO for Romarco), and Tom Kilbey, Professional Geologist (Sr. Geologist for Romarco) each being a designated "Qualified Person" under NI 43-101.

Romarco Minerals Inc. is a gold development company focused on production in the US and Mexico. The Company's flagship project is the Haile Gold Mine in South Carolina which is currently undergoing exploration drilling, bankable feasibility study and permitting. The Pinos Gold District in Mexico is a high grade epithermal vein district that is in the advanced exploration stage.

ON BEHALF OF ROMARCO MINERALS INC.

Diane R. Garrett, President & CEO

The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this press release.

Contacts: Romarco Minerals Inc. Diane Garrett President and C.E.O. (830) 624-6249 Romarco Minerals Inc. Shirene Urton Executive Assistant (775) 355-1900 Email: info@romarco.com Website: www.romarco.com