DOW JONES NEWSWIRES
The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.
Exxon Mobil Corp. (XOM) said a coker compressor shut down Jan 4. at its 240,000 barrel-a-day refinery near Joliet, Ill.
ConocoPhillips (COP) is conducting planned maintenance at its 139,000 barrel-a-day refinery in Los Angeles, a company spokesman said Jan. 4. The spokesman declined to specify which units were involved and how long the maintenane work would last.
Tesoro Corp. said flaring would take place for two days at its 97,000 barrel-a-day refinery in Wilmington, Calif., as a result of the restart of a crude and coker unit beginning Dec 29.
Sunoco Inc. (SUN) took down a hydrotreater unit at its 335,000 barrel-a-day refinery in Philadelphia, Penn., for maintenance, a person familiar with the refinery said on Dec. 15. It was unknown how long the unit would be offline.
ConocoPhillips (COP) said a process unit upset and coke drum fire occurred at its Wood River refinery in Roxana, Illinois, on Dec. 9, a filing to Illinois state environmental regulators said.
Hovensa on Dec. 6 said scheduled fourth-quarter maintenance and upgrade projects have been completed at its oil refinery in St. Croix, part of the U.S. Virgin Islands. No units were shut down completely to conduct the work, the company said in early October, noting that there would be no impact on customers.
For more detailed information, search Dow Jones Newswires using the code N/REF. Operator Refinery Capacity Description Restart (in 000s bbl/day) UNPLANNED CANADA Syncrude Alberta 300.0 Coker unit restarted at two- Dec 6 thirds of rated capacity, the Co. said on Dec 6. The unit was shut Nov. 22 for unplanned repair. CARIBBEAN EAST COAST Sunoco Philadelphia 225.0 Point Breeze Hydrotreater re- Dec 7 started on Dec 7; shut down oc- curred on Nov. 15, - filing. Sunoco Philadelphia 335.0 Girard Point Isomerization Unit N/A PA placed in circulation mode on Nov. 26 - filing. GULF COAST Exxon Beaumont TX 344.0 Operations returned to normal Dec 10 Mobil following a brief sulfur plant upset on Dec 10. The incident was expected to have some impact to production - filing. Pasadena Pasadena TX 100.0 Coker unit shut on Dec 10 due to N/A Refining fire. One man injured. Fire con- tained; cause under investigation. Total Port Arthur 174.0 Unit 890 shut on Nov. 29; No. N/A TX 30 coker flare utilized. MIDWEST Conoco Roxana, IL 356.0 Coke drum fire and process unit N/A Phillips upset on Dec 9, a filing to regulators said. Impact to pro- duction unclear. ROCKIES Sinclair Sinclair 74.0 Refinery at reduced rates fol- WY lowing fires at CDU on Sept. 3 and Sept. 4. Repairs underway. Plant continues to operate at re- duced rates, sources said Nov. 11. WEST COAST Chevron El Segundo 273.0 Refinery has resumed normal op- Dec 7 CA erations following Dec 1 power snag the co. said on Dec 7. Tesoro Martinez, CA 166.0 Plant returning to normal opera- Dec 5 tions on Dec 5 following Nov 28 distillation unit shutdown. PLANNED CANADA CARIBBEAN Hovensa St. Croix 350.0 Planned maintenance and capital Dec 6 project concluded, the co. said on Dec 6. EAST COAST Conoco Trainer, PA 185.0 Crude processing halted; operations winding down, the company said on Sept. 30. The refinery will be shuttered in six months if not sold. Sunoco Philadelphia 335.0 Refineries up for sale on July Marcus Hook 190.0 Sept. 6; Marcus Hook shut 2012 Dec. 1 ahead of schedule due to poor refining econo- mics. Phila. to shut in July. GULF COAST Conoco Belle Chasse 247.0 Refinery up for sale a Phillips LA Nov. 29 Bloomberg News report said. Conoco Sweeny, TX 247.0 Excess opacity reported on Dec N/A Phillips 9; company said planned work under way but didn't provide details. CVR Wynnewood 54.0 Maintenance turnaround for up 4Q Energy OK to 40 days starting in 3Q 2013. 2012 Holly Artesia, NM 100.0 Crude runs will be reduced by Early Frontier 50% during 30 days of major turn- 2012 maintenance in early 2012, the Co. said on Aug. 5. Motiva Port Arthur 285.0 Expansion project to increase 1Q TX throughput capacity by 325,000 2012 b/d, to 610,000-b/d, slowed. Completion now seen 1Q 2012, from 2010. Valero McKee TX 170.0 Vacuum unit turnaround planned for first half of 2012, company said. Expansion project announced March 2011 to increase crude oil throughput by 25,000 b/d to 195,000 b/d. Valero Houston,TX 88.0 Seven weeks of FCCU maintnance end-March starting in Feb. 2012 the Co. said on Nov. 1, 2011. Valero Norco, LA 185.0 Ten weeks of work planned for mid-April the crude and coker units start- 2012 ing Feb. 2012, co said on Nov. 1, 2011. Valero Norco, LA 185.0 Hydrocracker project will pro- 2013 ceed and be completed in late 2013, the co. said on 7/27/10. Upgrade project to build 2012 a new diesel hydrotreater unit moved from 2010 to 4Q 2012. Valero Port Arthur 325.0 Hydrocracker project will pro- 2012 TX ceed and be completed in late 2012. MIDWEST CVR Coffeyville 115.7 Second phase of turnaround work Q1 KS planned for Feb. 2012; first 2012 phase concluded in Nov. 2011. CVR Wynnewood 54.0 30-40 days maintenance planned Q3 OK in 3rd Q 2013, the co. said on 2013 Nov. 3, 2011. Holly Tulsa, OK 125.0 The entire refinery will be shut Late Frontier while West Plant section under- 2012 goes major turnaround maintenance in late 2012, the Co. said on Aug. 5, 2011. Husky Lima, OH 160.0 15-days of maintenance planned at Energy at aromatics unit in the fall of 2012. Husky Toledo, OH 140.0 Two turnarounds planned in 4Q 4thQ Energy 2011; one for two weeks, one for 2011 25 days. The plant will run at 90% of capacity during work, the co. said on Nov. 3, 2011. Marathon Canton, OH 78.0 Chemical release reported on N/A Nov. 26 due to unit shutdown for planned maintenance, the co. said on Nov. 27. Tesoro Mandan, ND 58.0 Total crude-oil processing capa- 2nd Q city to increase by 17% to 68,000 2012 b/d by 2nd quarter 2012. Valero Memphis, TN 180.0 Five weeks of maintenance on early-April crude unit starting in March. 2012 2012, co. said on Nov. 1, 2011. WEST COAST BP Carson, CA 265.0 Planned flaring will occur be- Dec 27 tween Nov 27 and Dec 27, a filing to regulators said. Flaring associated with planned maintenance, a source said. Chevron El Segundo 280.0 Planned flaring event will be- CA on Nov. 29 through Dec 1. Could be associated with FCCU restart. 4 weeks of maintenance at FCCU Early beginning late Oct. seen ending Dec in December, sources said on Nov. 18. Tesoro West Coast N/A Q4 2011 maintenance at West Coast refineries delayed until 2012. Further details not pro vided. Valero Wilmington, 78.0 Four weeks of maintenance for Feb. 2012 CA crude and coker units starting in January 2012, Co. said on Nov. 1, 2011.
1 Year Sable Offshore Chart |
1 Month Sable Offshore Chart |
It looks like you are not logged in. Click the button below to log in and keep track of your recent history.
Support: +44 (0) 203 8794 460 | support@advfn.com
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions