DOW JONES NEWSWIRES
The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.
Citgo Corp. Thursday said unit processing rates were adjusted in the East Plant section of its Corpus Christi, Texas, oil refinery due to unplanned upsets triggered by an early-day carryover of hydrocarbons, a filing to Texas state environmental regulators said.
BP PLC (BP, BP.LN) Thursday told California state environmental regulators that planned flaring not related to equipment failure would begin on Friday and last through all of Wednesday at its Los Angeles-area oil refinery in Carson.
Exxon Mobil Corp. (XOM) said Thursday that the failure of unspecified equipment at its oil refinery in Beaumont, Texas, on Wednesday will have an impact on production.
Tesoro Corp.'s (TSO) refinery in Mandan, N.D., is running at 90% of capacity after a January fire damaged a furnace at the plant's alkylation unit, a company spokesman said Thursday.
Alon USA (ALJ) said Wednesday sulfur recovery units at its oil refinery in Big Spring, Texas, went off-line, but the reason for the outages wasn't yet known. There is no estimate for the restart of the units.
Crude oil throughput and production rates at Hovensa's (HES) oil refinery on the U.S. Virgin Island of St. Croix will soon return to newly established normal rates following the completion of scheduled turnaround maintenance at one of the plant's sulfur recover units, a company spokesman said Tuesday.
Operations at Marathon Oil Corp.'s (MRO) oil refinery in Texas City, Texas, returned to normal late in the day Monday following an afternoon power disruption within the plant, a filing to Texas state environmental regulators made available on Tuesday said.
Valero Energy Corp. (VLO) said Tuesday the process of shutting down a 90,000-barrels-a-day crude distillation unit for 24 days of planned turnaround maintenance at its Houston refinery got under way on Monday.
Exxon Mobil Corp. (XOM) said Tuesday that several weeks of scheduled turnaround maintenance got under way earlier in the day at a hydrocracking unit, a saturated gas plant and one of the hydrogen units at its Torrance, Calif.,, refinery.
Tesoro Corp. (TSO) said Tuesday that its Mandan, N.D., refinery continues to operate at minimally reduced rates following a fire at the plant's alkylation unit furnace on Jan. 19. No estimate yet on when the alkylation unit will restart and the return to normal operations.
Holly Corp.'s (HOC) Navajo oil refinery in Artesia, N.M., has been operating at 40% of capacity, or 40,000 barrels a day, since a plantwide power failure on Jan. 26 due to an interruption in power supply from its local utility, the company said in a statement Monday. Return to normal operations expected in "several more days," the company said on Monday.
ConocoPhillips (COP) said Monday that a leak and fire Sunday at its San Francisco-area oil refinery in Rodeo, Calif., occurred at the plant's coker unit. The company did not comment on the impact on operations.
Marathon Oil Corp. (MRO) said Sunday that a leak of isobutane vapor at it's oil refinery in Texas City, Texas, on Saturday did not cause any injuries and that the "all clear" was sounded after the leak was stopped, allowing residents to return to their homes after being evacuated. The leak did not impact operations.
Flint Hills Resources confirms brief fire Sunday at east plant FCCU II, but would not say whether the event had an impact on operations.
Valero Energy Corp. (VLO) said Friday that its Aruba refinery is nearing planned rates after being offline for roughly 18 months. The company also announced turnaround plans at six of its refineries in the first and second quarters of 2011 on Wednesday.
For more detailed information, search Dow Jones Newswires using the code N/REF. Operator Refinery Capacity Description Restart (in 000s bbl/day) UNPLANNED CANADA CARIBBEAN EAST COAST Sunoco Marcus Hook 178.0 Reformer, Crude Unit, gas plant 1st Q PA shut Jan. 7 for maintenance, a 2011 source said on Jan. 6. Co. said on Feb. 3 work will conclude 1st quarter 2011. Sunoco Philadelphia 335.0 Crude unit, FCCU to shut Feb. 1st Q PA 1 for 2 weeks, a source said 2011 on Jan. 6. Co. said on Feb. 3 work will conclude in 1st quarter 2011. GULF COAST Citgo Corpus 163.0 East Plant unit rates adjusted Christi, TX following due to unplanned up- sets at Unibon and SRU on Feb 3. Impact on production unclear. Exxon Beaumont 344.5 Production to be impacted by un- TX specified equipment failure the co. said on Feb. 3. Flint Corpus 300.0 Fire at East Plant on Jan. 31 Hills Christi, TX results in excess opacity at FCCU II. Fire extinguished with- in 15 minutes. Company would not comment on status of FCCU operations. Holly Artesia 100.0 Refinery operating at 40,000 b/d Corp. NM since Jan. 26 following plant-wide power failure; return to normal will take several more days, the co. said on Jan. 31. Marathon Texas City 76.0 Operations returned to normal Jan. 31 TX late on Jan. 31 following an afternoon power disruption. Leak of isobutane vapor on Jan. 29 did not impact operations, the company said on Jan. 30. Valero Port Arthur 287.0 No impact to production from TX flaring at gulfining unit Jan. 23, 23, Co. said on Jan. 25. MIDWEST Tesoro Mandan, ND 58.0 Refinery continues to operate at 90% of capacity following fire at alkylation unit furnace on Jan. 19. All customer requirements are being met. Estimate to return to normal not yet available, the co. to normal by mid-March, the co. said on Feb. 3. ROCKIES WEST COAST Conoco Rodeo, CA 120.2 Leak and fire occurred Jan. 30 Phillips at coker unit, the Co. said on Jan. 31, but would not comment on impact on operations. PLANNED CANADA Shell Montreal 130.0 The refinery will be converted Quebec into a terminal. CARIBBEAN Hovensa St. Croix 500.0 Operations will soon return to USVI newly established rates as turn- around maintenance at SRU nears completion, the Co. said on Feb.1. The SRU turnaround began in Jan. Shutting smaller, older process units on west side of plant, which will reduce crude distillation to 350,000-b/d, Co. said Jan. 26. Coker, FCCU will not be affected. Valero Aruba 235.0 Plant nearing planned rates, the company said on Jan. 28. The plant, shut in July 2009 on poor economics, will use LNG to reduce utility costs. EAST COAST Sunoco Westville 145.0 Idling all Eagle Point refin- n/a NJ ing operations indefinitely due to poor economics, co. said Oct. 6, 2009. Valero Delaware 210.0 PBF Energy has closed Apr deal to buy plant. Petroplus 2011 said May 5 the plant would be restarted in 2Q of 2011. Valero Paulsboro, 185.0 Sale of refinery to PBF Energy Dec.17 NJ completed on Dec. 17. Western Yorktown 64.5 The refinery will close in Sept VA September 2010 for economic reasons. Terminal operations will continue. GULF COAST BP Texas City 437.0 A crude unit is going into TX turnaround maintenance as similar work is being done on FCCU No. 1, which was taken out of service on Jan. 12, a person familiar with ops said Jan. 25. Chevron Pascagoula 330.0 Pre-commercial heavy oil 2010 Miss. conversion project delayed from 2008 to 2010 due to
economic factors. Expansion project including the replacement of two 30-year- old reformers and construction of a 55,000 b/d continuous catalytic reformer platformer unit to be completed by late summer, Industrial Info Resources said July 6. A premium base-oil facility was also being planned, co. said in late Feb. Exxon Baytown, TX 560.6 New ULSD Units commissioned, Co. said Oct 21. ULSD supply will increase by over 3 million gallons from Baytown & Baton Rouge. Shell Deer Park 327.0 Maintenance activities are TX underway, Co. said Jan. 18, but the duration and type of work were not disclosed. Exxon Chalmette 120.0 Crude throughput will be re- N/A LA duced to 90,000-b/d as redun- dant units and about 70 jobs are taken out of service and cut for economic reason. These have begun to take place, the co. said Aug 26. FCCU was taken out of service on Jan. 22, but the rest of refinery is operational. Motiva Port Arthur 285.0 Expansion project to increase 1Q throughput capacity by 325,000 2012 b/d, to 610,000-b/d, slowed. Completion now seen 1Q 2012, from 2010. Valero Houston, TX 145.0 Shut down of 90,000-b/d CDU Feb. 24 got underway on Jan. 31/Feb. 1 for 24 days turnaround main- tenance, the Co. said on Feb. 1. Valero Corpus 340.0 West Plant 50,000-b/d FCCU at Christi, TX reduced rates since mid-Dec for economic reasons. Valero Norco, LA 250.0 Hydrocracker project will pro- 2013 ceed and be completed in late 2013, the co. said on July 27. FCCU, 100,000 b/d, will be 2Q revamped and work will take 2011 place at a alky unit, lasting 55 days starting in March, Co. said Oct. 26. Work planned at 90,000-b/d alky unit in March for 56 days. Upgrade project to build 2012 a new diesel hydrotreater unit moved from 2010 to 4Q 2012. Valero Port Arthur 325.0 Hydrocracker project will pro- 2012 TX ceed and be completed in late 2012, the co. said on July 27. Crude and coker work lasting 1H 2011 51 days to begin in February. Six coke drums will be re- 2011 placed in 2011. 77,000-b/d FCCU at reduced n/a rates since mid-Dec for economic reasons. Valero Sunray, TX 170.0 55,000-b/d FCCU at reduced n/a rates since mid-Dec for economic reasons. Planned hydrocracker turnaround, delayed from March, to take place in April and will last 24 days, Co. said Jan. 26. Flint Corpus 300.0 Final dust clearning for sulfur Hills Christi, TX recovery unit No. 3 on Jan. 19-20, so the new unit can be commissioned. Citgo Corpus 163.0 Turnaround activities in process Christi, TX and will continue to Feb. 28, Co. said Jan. 20. Sources said work is being performed at FCCU. New 42,500 B/D ULSD new unit has been started, now allowing the company to produce all of this fuel entirely in- house, Co. said Jan. 27. Pasadena Pasadena, TX 56.0 FCCU, 56,000-b/d, will be taken out of service Feb. 28 for 44 days for planned work, Co. reported Jan.25. MIDWEST Valero Ardmore, OK 90.0 Plantwide turnaround expected to take place in March 2011. CVR Coffeyville 115.7 Periodic turnaround will take place KS in two phases beginning in Fall 2011 and completed in Spring 2012. WEST COAST BP Carson, CA 264.0 Flaring, not related to equip- ment breakdown, planned between Feb. 4 and Feb. 12. Conoco Rodeo, CA 120.0 Planned maintenance underway, Co. said Jan. 20, but declined to say what units are involved and how long the work will last. Exxon Torrance 149.5 Hyrocracker, Sat. Gas Plant and Mobil CA hydrogen unit shut Feb 1 for several weeks of planned turnaround mainte- nance, the co. said on Feb. 1. Valero Benicia, CA 170.0 Process unit and FCCU down. FCCU unit to remain down amid maintenance planned for 1Q 2011. Plantwide turnaround is taking place and will last about 42 days, Co. reported Jan. 26. BP Carson, CA 264.0 Planned flaring activity to take place on Jan. 22-27, Co. reported Jan. 20.
1 Year CVR Energy Chart |
1 Month CVR Energy Chart |
It looks like you are not logged in. Click the button below to log in and keep track of your recent history.
Support: +44 (0) 203 8794 460 | support@advfn.com
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions