ADVFN Logo ADVFN

We could not find any results for:
Make sure your spelling is correct or try broadening your search.

Trending Now

Toplists

It looks like you aren't logged in.
Click the button below to log in and view your recent history.

Hot Features

Registration Strip Icon for discussion Register to chat with like-minded investors on our interactive forums.

GLNG Golar LNG Limited

24.2958
-0.6342 (-2.54%)
04 May 2024 - Closed
Delayed by 15 minutes
Share Name Share Symbol Market Type
Golar LNG Limited NASDAQ:GLNG NASDAQ Common Stock
  Price Change % Change Share Price Bid Price Offer Price High Price Low Price Open Price Shares Traded Last Trade
  -0.6342 -2.54% 24.2958 24.00 26.44 25.19 24.66 25.19 706,744 01:00:00

FLNG Gimi Force Majeure claim

07/04/2020 2:45pm

GlobeNewswire Inc.


Golar LNG (NASDAQ:GLNG)
Historical Stock Chart


From May 2019 to May 2024

Click Here for more Golar LNG Charts.

Gimi MS Corp. (the “Company”), a subsidiary of Golar LNG Ltd (Nasdaq: GLNG), received written notification of a force majeure claim (the “Notice”) from BP Mauritania Investments Ltd (“BP”) under the Lease and Operate Agreement, dated February 26, 2019, between the Company and BP (the “Agreement”), relating to the Greater Tortue Ahmeyim project.

The Notice received from BP claims that due to the recent outbreak of the novel coronavirus (COVID-19) around the globe, BP is not able to be ready to receive the floating liquefied natural gas facility “GIMI” on the target connection date in 2022. 

BP estimates at this stage that the consequential delay caused by the claimed force majeure event is in the order of one year and that it is not currently possible to mitigate or shorten this delay. Golar has asked BP to clarify how a force majeure event discovered as recently as the end of March 2020 could immediately impact the schedule by an estimated one year. 

Based on the information received as of today the Company is engaging in clarification and an active dialogue with BP to establish the duration of the delay and the extent to which this has been caused by the claimed force majeure event. However, in anticipation of a potential delay, the Company has commenced discussions with its main building contractor, Keppel Shipyard Limited (“Keppel”), to re-schedule activities in order to reduce and reprofile its capital spending commitments for 2020 and 2021.

The Company is evaluating the Notice and reserves all of its rights under the Agreement. 

Hamilton, Bermuda

April 7, 2020

Enquiries:

Golar Management Limited: + 44 207 063 7900

Stuart Buchanan

1 Year Golar LNG Chart

1 Year Golar LNG Chart

1 Month Golar LNG Chart

1 Month Golar LNG Chart

Your Recent History

Delayed Upgrade Clock