White Energy Company Limited (ASX: WEC) today announced the completion
of construction of the Company’s commercial
scale production plant at Cessnock, New South Wales. The Cessnock Plant,
which utilises White Energy’s licensed
binderless coal briquetting technology, to upgrade lower rank coal to
significantly increase its energy efficiency, has an installed capacity
of 90,000 tonnes per annum.
The Cessnock Plant was completed on schedule and in line with budget
estimates. White Energy’s internal
commissioning team has taken over the Plant and has begun the cold
commissioning phase, which involves the testing of the various
components of the Plant. This will be followed by a hot commissioning
program which will involve the processing of significant quantities of
feedstock coal to ensure the optimal functioning of the Plant. It is
envisaged that the commissioning phases will conclude in approximately
six weeks at which point the Cessnock Plant will be in full production
mode.
White Energy’s Managing Director, Mr John
Atkinson says “The completion of White Energy’s
first commercial production plant represents a significant milestone for
the Company.
“We are delighted that the Cessnock Plant has
been built on time and on budget. It is obviously an exciting time for
the Company to now have an operating facility available to upgrade coal
for commercial and developmental purposes. But just as exciting is the
fact that we will soon be processing coal for power companies to use to
conduct combustion tests and trial burns some months in advance of what
was originally forecast. ”
The Cessnock Plant is White Energy’s premier
production, testing and showcase facility in Australia. The Plant uses
White Energy’s licensed and patented process
to upgrade sub-bituminous coal into a higher energy, more stable,
cleaner burning coal briquette. The upgraded product can be transported
and handled like normal coal, but has significant transportation cost
benefits, combustion advantages and, importantly, is a cleaner fuel from
an emissions perspective when compared to the burning of traditional
thermal coal.
The design and construction of the Cessnock Plant, is representative of
the design and construction process required for the one million tonne
per annum commercial plant currently being built by White Energy, in
joint venture with Bayan International Pte Ltd, at Tabang, East
Kalimantan, Indonesia. The successful completion of construction of the
Cessnock Plant has provided invaluable practical experience for the
Company ahead of building its one million tonne per annum plant at the
Tabang mine in Indonesia.
The Cessnock Plant will also be used for continued development purposes
and will be an important research and training facility for the Company.
White Energy will also be able to train its commissioning teams at the
Cessnock Plant in preparation for the commissioning of plants planned to
be built by the company in Indonesia, China and the United States of
America during 2009.
Prior to the completion of the Cessnock Plant, White Energy had secured
joint venture arrangements to construct plants with over 13MTPA of
installed capacity. The company expects that the completion of the
Cessnock Plant will generate further strong interest and demand from
overseas customers in Indonesia, China, USA and Africa, including large
international mining and investment houses, wishing to partner with
White Energy to construct plants using White Energy’s
technology.
White Energy has received continued strong support for it’s
cleaner coal upgrading technology from both the New South Wales and
Commonwealth Governments. In early May, during the final stages of
construction of the Plant, Senator the Hon Penny Wong, Minister for
Climate Change and Water and the Hon. Joel Fitzgibbon MP, Minister of
Defence and the Federal Member for Hunter, visited White Energy’s
Cessnock Plant.
Following this visit, Mr Fitzgibbon said, “White
Energy is to be congratulated on its commitment to cleaner coal
initiatives.
“The completion of construction of White
Energy’s cleaner coal production plant at
Cessnock, highlights the importance of the Hunter region in supporting
cleaner coal initiatives and how the region is playing a pivotal role in
Australia’s future energy policy.”
Government support of White Energy’s
commercialisation of its technology also included White Energy receiving
a A$4.35 million grant from the Commonwealth Government through
AusIndustry’s Commercial Ready innovation
grant program specifically for assisting the Company to build the
Cessnock Plant.
About White Energy
White Energy is the exclusive worldwide license holder of the Binderless
Coal Briquetting process that upgrades relatively poor quality coal to
significantly increase its energy efficiency. The process was developed
by CSIRO in conjunction with TraDet Inc, K.R. Komarek Inc and The
Griffin Coal Mining Company Pty Ltd. The patented process involves the
crushing, drying and briquetting of high moisture coals, resulting in
the reduction of the moisture content of the coal and converting the
product into a higher energy content, stable briquette. The advantages
of the White Energy process involve creating a higher energy value coal,
creating a physically and chemically stable product, significantly
reducing coal transportation costs and creating a higher energy value
release with lower carbon emissions. The process has been shown to be
cost and operationally superior to competing technologies.
The White Energy technology also represents a first step in building a
cleaner coal solution. White Energy’s process
is an important first step – an evolutionary
process that speeds the maturation of lower grade coals. White Energy is
committed to delivering cleaner coal technologies with a view to
ultimately achieving zero emission targets.
White Energy is in the process of commercialising this technology and is
currently constructing a commercial one million tonne per annum plant in
Indonesia in joint venture with Bayan Resources. The Company also has a
joint venture agreement with Adaro Group, one of Indonesia’s
largest coal companies and Itochu Corporation, a major Japanese trading
house respectively, to build additional coal upgrading plants in
Indonesia. Further, White Energy has also signed a Heads of Agreement
with Datang International Power Generation Company in relation to the
development of coal upgrading plants in China. Most recently, the
Company has entered into a development agreement with NRG Energy and
Buckskin Mining in respect of a potential project in USA. In addition to
these projects, the company is actively pursuing opportunities to deploy
its technology across various markets including Indonesia, China, India,
Mongolia, Africa and the USA.
This press release contains forward-looking statements that are
subject to risks and uncertainties. These forward-looking statements
include information about possible or assumed future results of our
business, financial condition, liquidity, results of operations, plans
and objectives. In some cases, you may identify forward-looking
statements by words such as "may," "should," "plan," "intend,"
"potential," "continue," "believe," "expect," "predict," "anticipate"
and "estimate," the negative of these words or other comparable words.
These statements are only predictions. One should not place undue
reliance on these forward-looking statements. The forward-looking
statements are qualified by their terms and/or important factors, many
of which are outside the Company's control, involve a number of risks,
uncertainties and other factors that could cause actual results and
events to differ materially from the statements made. The
forward-looking statements are based on the Company's beliefs,
assumptions and expectations of our future performance, taking into
account information currently available to the Company. These beliefs,
assumptions and expectations can change as a result of many possible
events or factors, including those events and factors described in "Risk
Factors" in the prospectus, not all of which are known to the Company.
Neither the Company nor any other person assumes responsibility for the
accuracy or completeness of these statements. The Company will update
the information in this press release only to the extent required under
applicable securities laws. If a change occurs, the Company's business,
financial condition, liquidity and results of operations may vary
materially from those expressed in the aforementioned forward-looking
statements.