The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.
Most recently, Flint Hills Resources on March 19 confirmed the shut one of three processing units at its Alaska refinery due to low jet fuel demand.
Valero Energy Corp. (VLO) on March 19 said the gasoline-making FCCU at its Ardmore, Okla., refinery was back at normal processing rates following its March 11 unplanned shutdown.
Valero restarted on March 19 crude unit No. 1 at the West Plant section of its Corpus Christi, Texas, refinery. The unit was shut in mid-January for planned turnaround maintenance.
ExxonMobil (XOM) will restart on March 19 a hydrogen plant at its Torrance, Calif., refinery. The plant, one of two at the facility, has been off-line since fourth-quarter 2008.
And Valero Energy on March 18 restarted crude unit No. 4 and a vacuum unit located in the East Plant section of the Corpus Christi refinery. The units were shut on March 17 to repair a leak in an exchanger.
Planned turnaround maintenance is ongoing on March 17 at one of three crude units at BP's (BP) Whiting, Indiana, refinery. The 30-40 days of maintenance started earlier this month and is seen concluding by the end of the month or by early April.
Alon USA (ALJ) reported a sulfur recover units snag on March 16 at it's Big Spring, Texas, refinery; the problem did not have an impact on the refinery's operations.
Planned turnaround maintenance continues on March 16 at ConocoPhillips' (COP) Rodeo, Calif., refinery's hydrocracker and reformer units. The work, slated to take 45 days, is expected to conclude around April 15 and will cause intermittent flaring events, company personnel said.
Marathon Oil Corp. (MRO) on March 16 confirmed the shutdown of a crude unit and two coker units on March 9 at its Robinson, Illinois, refinery for planned turnaround maintenance; no restart estimate was given.
Tesoro (TSO) on March 14 began 17-days of planned work at a coker and reformer unit at its Wilmington, Calif. refinery. The work is expected to have minimal impact on product output, the Co. said.
Harvest Energy Trust (HTE) will shut its entire North Atlantic refinery in Newfoundland in the first week of April for 21-days to facilitate planned maintenance and upgrade work. Work to increase the plant's hydrocracker capacity by 1,000-barrels-a-day, to 38,000-barrels a day, will continue for an addition 14 days.
For more detailed information, search Dow Jones Newswires using the code N/REF.
UNPLANNED Operator Refinery Capacity Description Restart (in 000s bbl/day) EAST COAST Sunoco Philadel- 335.0 10 workers hospitalized n/a phia, PA Mar. 11 for evaluation after vapor release at alkylation unit. Valero Delaware 210.0 30-day plant-wide shutdown Apr.3 DE begins March 4 to better fac- ilitate repairs at the coker unit which has been shuttered since Feb. 15. FCCU at reduced n/a rates since mid-Dec. for eco- mic reasons. CARIBBEAN GULF COAST Delek US Tyler, TX 60.0 Refinery expected to be wholly May on-line by May 2009, following Nov. 20 fire at sat. gas unit killed two workers and injured others. Total Port Arthur 232.0 Work to repair leak at Mar 25 unit 812 starts Mar. 11. Unit not identified other than by number. Valero Corpus 340.0 Crude and Vacuum Unit shut Mar 18 Christi, TX restarted Mar. 18 following one day of repairs to fix a leak at an exchanger. Valero Port Arthur 325.0 FCCU at reduced rates since n/a mid-Dec. for economic rea- sons. MIDWEST Valero Ardmore, OK 90.0 FCCU shut Mar. 11 is back Mar 19 at normal rates on Mar. 19. WEST COAST Conoco Wilmington, 105.0 Refinery ramping up to- Mar 12 CA wards normal operations after Mar. 11 power failure. Flint North Pole 210.0 One of three processing n/a Hills units has been shut due to low jet fuel demand, the co. confirmed on Mar. 19. PetroStar Valdez, AK 48.0 Refinery shut due to Dec. n/a 28 fire. Tesoro Martinez 166.0 Hyrdrocracker production Feb 27 CA slowed while work done on valve. Co. expects rate to return to normal at the end of week of Feb. 23 Tesoro Kenai 72.0 Power outage, refinery to be Feb. 24 Alaska restarted by end of Feb. 24th PLANNED CANADA North Newfound- 115.0 Plantwide shutdown will begin Early Atlantic land first week of April for 21 May days of planned maintenance. Upgrade work at hydrotreater will take an additional 14 days. EAST COAST Conoco Linden 238.0 145,000-b/d FCCU shut Feb. end- NJ 18 for about 45 days of March planned turnaround mainte- nance. Sunoco Philadelphia 330.0 Reformer unit shut in early n/a PA Oct. for economic reasons. Shutdown to last one to six months. Valero Delaware 210.0 Entire refinery shut Mar. 4 Apr 3 City, DE for 30 days maintenance at coker unit. 82,000-b/d FCCU operating n/a at reduced rate for eco- nomic reasons, Co. said on Dec. 16. Valero Paulsboro 160.0 27,000-b/d coker unit to n/a NJ shut in April for 35-days of planned work, the Co. said on Mar. 11. GULF COAST Chevron Pascagoula 330.0 Pre-commercial heavy oil 2010 LA conversion project delayed from 2008 to 2010 due to economic factors. Conoco Sweeny, TX 247.0 Several process units restart Mar. on March 8 following about 18 6-weeks of planned maintenance. Flint Corpus 288.1 $250 mil. project for new Spr Hills Christi, TX diesel desulfurization, 2010 sulfur recovery unit to begin in Fall 2008. Construction to last 18 months. Marathon Garyville 245.0 Project to increase crude oil 4Q LA refining capacity by 180,000- 2009 b/d expected to conclude in 4th-quarter, 2009. Marathon Texas City 76.0 Platformer and UDEX shut for n/a TX annual planned maintenance and catalyst change on Feb. 4. Valero Corpus 340.0 West Plant Crude Unit No. 1 Mar 19 Christi, TX restarted Mar. 19. The unit was shut in mid-Jan. for turnaround maintenance. 20,000-b/d FCCU in East n/a Plant shut; West Plant 50,000-b/d FCCU at reduced rates since mid-Dec. for economic reasons. Valero McKee, TX 170.0 Smaller of two crude units May/ at 60,000-b/d to shut in June May for 14 days; 55,000-b/d to shut in May for 21 days. Valero Norco, LA 250.0 Upgrade project to build 2012 a new diesel hydrotreater unit moved from 2010 to 4th-quarter 2012, the Co. said on Jan. 27. Valero Port Arthur 325.0 77,000-b/d FCCU at reduced n/a TX rates since mid-Dec. for economic reasons. Valero Sunray, TX 170.0 55,000-b/d FCCU at reduced n/a
rates since mid-Dec. for economic reasons. Valero Texas City, 245.0 All units back on-line. Mar.9 TX Refinery in sequential re- start on March 1 following 40-days maintenance at crude and coker units during which the entire refinery was shut- terred for economic reasons. Valero Three Rivers 95.0 24,000-b/d FCCU at reduced n/a TX rates since mid-Dec. for economic reasons. MID-CONTINENT BP Whiting, 410.0 Planned maintenane continues End IN on Mar. 16 at the smaller of Mar 3 crude units. The work began in early March and is expected Early to conclude by the end of the Apr month or by early April. Conoco Billings, 61.0 On Mar. 5 the Co. delayed for Jan. MT one year an expansion project 2010 which will increase capacity to 71,000 bbls. Construction of a new crude is now scheduled to begin in January 2010. Frontier El Dorado 110.0 A coker turnaround and expan- Mid- KS sion project was delayed until Aug. Mid-July, and subsequently delayed until August. Marathon Robinson 204.0 Crude unit, two coker units n/a shut Mar. 9 for planned main- tenance; no restart timing available. Marathon Detroit 100.0 Project to upgrade refinery n/a MI to process Canadian crude delayed from 2009 to 2012, the co. said on Feb. 3. Sunoco Toledo, OH 160.0 FCCU turnaround lasting 6 weeks 4Q08 planned for 4q 2008 or 1Q 2009 Sunoco Tulsa, Okla. 85.0 Turnaround maintenance will n/a take place in Feb., the Co. said on Feb. 5. Refinery could close by end of 2009 if buyer not found. Valero Memphis, TN 195.0 FCCU upgrade originally slated 2012 for completion in 2009 has been shifted to 2012, the Co. said on Jan. 27. ROCKY MOUNTAINS Suncor Commerce City 90.0 32,000-b/d crude unit, n/a CO 10,500-b/d reformer will shut in March for planned maintenance, the Co. said on Jan. 26. WEST COAST Alon Paramount 55.0 Hydrocracker project post- poned indefinitely, the Co. said on Feb. 4 BP Carson, 260.0 30-days of planned mainte- Apr 6 CA nance starts March 7-8 at 20,000-b/d reformer. Conoco Rodeo, CA 155.0 Faring reported on Mar. Apr 15 14 as a result of on-going turnaround maintenance at the hydrocracker and reformer. Exxon Torrance, 155.0 Hydrogen plant to restart Mar 19 CA Mar. 19. The plant has been shuttered for planned main- tenance since 4th-quarter 2008. Shell Anacortes 145.0 Units to shut for 60 days mid Apr Wash. work beginning in late Feb. Tesoro Wilmington 105.0 Reformer and coker unit shut Mar 30 Mar. 13 for 17-days of plan- ned maintenance. Valero Benecia 170.0 37,000-b/d hydrocracker to March CA undergo 14-days of planned maintenance in March, a month later then the Co. originally planned, but the work hasn't started as of March 8, co. said.
1 Year Casino Guichard Perrachon Chart |
1 Month Casino Guichard Perrachon Chart |
It looks like you are not logged in. Click the button below to log in and keep track of your recent history.
Support: +44 (0) 203 8794 460 | support@advfn.com
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions