We could not find any results for:
Make sure your spelling is correct or try broadening your search.
Share Name | Share Symbol | Market | Type | Share ISIN | Share Description |
---|---|---|---|---|---|
Tharisa Plc | LSE:THS | London | Ordinary Share | CY0103562118 | ORD USD0.001 (DI) |
Price Change | % Change | Share Price | Bid Price | Offer Price | High Price | Low Price | Open Price | Shares Traded | Last Trade | |
---|---|---|---|---|---|---|---|---|---|---|
0.00 | 0.00% | 68.00 | 67.00 | 69.00 | 68.00 | 68.00 | 68.00 | 5,000 | 08:00:28 |
Industry Sector | Turnover | Profit | EPS - Basic | PE Ratio | Market Cap |
---|---|---|---|---|---|
Miscellaneous Metal Ores,nec | 649.89M | 82.24M | 0.2743 | 2.52 | 206.86M |
TIDMTHS
RNS Number : 4535K
Tharisa PLC
10 July 2017
Tharisa plc
(Incorporated in the Republic of Cyprus with limited liability)
(Registration number HE223412)
JSE share code: THA
LSE share code: THS
ISIN: CY0103562118
('Tharisa')
Third quarter production report for the period ended 30 June 2017
Another record quarter for Tharisa
Highlights for the three months ended 30 June 2017
-- Record quarterly reef mined of 1 275.2 kt continues to exceed the required run rate of 4.8 Mtpa on an annualised basis
-- Record chrome concentrate production of 333.9 kt, up 6.1% quarter on quarter
-- Record specialty chrome production of 87.1 kt, 26.1% of total chrome production and up 15.5% quarter on quarter
-- PGM production of 35.4 koz, up 3.2% quarter-on-quarter
-- Record PGM recoveries at 81.3% and chrome recoveries at 66.0% exceeding targeted recoveries of 80.0% and 65.0% respectively
Commenting on Q3 production, Tharisa CEO Phoevos Pouroulis, said:
"Tharisa Minerals has again shown incremental improvements in production volumes and recoveries. We continue to examine ways to further optimise our operations and look forward to achieving our targeted recoveries and production outlook for the financial year."
Safety
Safety remains a top priority and Tharisa continues to strive for zero harm at its operations. There were no lost time injuries during the quarter and consequently we recorded an improved LTIFR of 0.08 per 200 000 man hours worked.
Production update
The production update for the quarter ended 30 June 2017 is as follows:
Quarter on Nine months Quarter ended Quarter ended quarter ended 30 June 31 March movement Quarter ended 30 June 2017 2017 % 30 June 2016 2017 ------------------- ---------------- --------------- --------------- -------------- --------------- ------------ Reef mined kt 1 275.2 1 219.2 4.6 1 235.4 3 724.3 m(3) waste/m(3) Stripping ratio reef 6.9 7.5 7.4 7.8 Reef milled kt 1 199.1 1 211.3 (1.0) 1 192.2 3 616.8 PGM flotation feed tonnes kt 866.0 897.9 (3.6) 929.6 2 648.9 PGM rougher feed grade g/t 1.57 1.56 0.6 1.64 1.55 6E PGMs produced koz 35.4 34.3 3.2 33.5 104.6 PGM recovery % 81.3 76.2 6.7 68.5 79.3 Average PGM contained metal basket price US$/oz 792 783 1.1 745 771 Average PGM contained metal basket price ZAR/oz 10 443 10 355 0.8 11 162 10 352 Cr O ROM grade % 17.8 17.5 1.7 17.7 17.6 Chrome recovery % 66.0 62.5 5.6 61.6 64.3 Chrome yield % 27.8 26.0 6.9 25.8 26.8 Chrome concentrates produced kt 333.9 314.6 6.1 307.1 970.7 --------------- --------------- -------------- --------------- ------------ Metallurgical grade kt 246.8 239.2 3.2 225.6 731.1 Specialty grades kt 87.1 75.4 15.5 81.5 239.6 --------------- --------------- -------------- --------------- ------------ Metallurgical grade chrome concentrate contract price US$/t CIF China 147 338 (56.5) 105 212 Metallurgical grade chrome concentrate contract price ZAR/t CIF China 1 892 4 430 (57.3) 1 589 2 844 Average exchange rate ZAR:US$ 13.2 13.2 - 15.0 13.5 ------------------- ---------------- --------------- --------------- -------------- --------------- ------------
Mining
Reef mined from the open pit totalled a record 1 275.2 kt for the quarter. This is a 5% improvement on the 1 219.2 kt mined in Q2 and brings the monthly average to 413.8 kt over the first nine months of FY2017. The increase in production is mainly attributable to a focus on continuous improvement initiatives particularly in the drill and blast operations. The benefits of these initiatives, in terms of the availability and utilisation of mining equipment, should continue into Q4.
Total waste of approximately 2.5 Mm(3) was moved during the quarter at a stripping ratio of 6.9 on a m(3) :m(3) basis. The waste stripping remained below the LOM average of 9.7 as the team's focus remained on interburden stripping to ensure access to the reef horizons. The lower stripping ratio was also due to the planned pit extension following the road diversion. The benefits of the shorter waste hauling distances associated with the road diversion will be delivered in the latter part of Q4. It is forecast that stripping for Q4 will be above 9 m(3) :m(3) .
In addition to the focus on increasing waste stripping ahead of ore mining to ensure sustained access to the reef horizons, there is a continued emphasis on mining consistent reef grades for feed into the processing plants.
Processing
During the quarter 1 199.1 kt of ore was milled, resulting in PGM production of 35.4 koz on a 6E basis and record chrome production of 333.9 kt, 87.1 kt (26.1%) of which are specialty grade concentrates.
The chrome feed grade improved by 2% while the 6E PGM rougher feed grade remained consistent compared to the previous quarter. The marginally lower mill throughput for Q3 was due to the timing of the planned maintenance during the quarter.
The continuous improvement initiatives focused on crusher throughput and improved crusher run time. The positive impact of these initiatives on plant throughput was evidenced towards the end of Q3 and will flow into Q4. Despite the marginally lower throughput, the total PGM and chrome production increased by 3% and 6% respectively when compared to Q2.
Both PGM and chrome recoveries exceeded target during the quarter with PGM recoveries at 81.3%, against a target of 80%, and chrome recoveries at 66.0%, against a target of 65%.
The high energy flotation successfully implemented at the Voyager PGM recovery circuit has been incorporated into the PGM recovery circuit of the Genesis Plant and is scheduled to be completed by the end of July 2017. This will contribute to improved PGM production in Q4, although production may be partially impacted by the planned oxidized ore being mined as the open pit is extended through the road diversion area.
Market update
The average per ounce PGM basket price for the three months ended June 2017 was US$792 (ZAR10 443), which is US$9 an ounce higher than the US$783 (ZAR10 355) price achieved in the quarter ended March 2017.
While contracted metallurgical grade chrome concentrate prices decreased to US$147 per tonne from US$338 per tonne, there are signs that prices have found a floor and there is increased price stability within the chrome concentrate market. Despite Chinese port stock levels of 2.46 Mt, liquidity has returned on the back of continued stainless steel demand and consumption out of China. The fundamentals of the global stainless steel market remain sound with continued growth forecast in 2017, further supporting strong demand for chrome units in the form of ferrochrome and chrome ores. Specialty chrome concentrates, which comprise 26.1% of total chrome concentrate production and which supplies the chemical and foundry markets, continue to attract a premium above the contracted metallurgical chrome concentrate prices.
Transition to owner mining model
Tharisa Minerals entered into a binding term sheet with MCC Contracts Proprietary Limited (MCC) on 10 May 2017 in terms of which Tharisa Minerals will purchase, subject to the fulfilment of certain conditions precedent, certain of MCC's existing equipment, strategic components, site infrastructure and spare parts, and transfer the employees currently deployed at its Tharisa Mine in South Africa.
On 6 July 2017, shareholders were advised that the transaction had been unconditionally approved by the South African Competition Commission. The effective date of the transaction will be the date immediately following the fulfilment or waiver, as applicable, of the remaining conditions precedent, or such later date as may be agreed between the parties. The long stop date for fulfilment of these conditions is 30 September 2017.
The change in the operating model is expected to have both cost and operational benefits as well as providing financial flexibility, thereby cementing Tharisa's low-cost high margin position.
New Mining Charter
The Mining Charter was first introduced in 2004 as a regulatory instrument aimed at initiating transformation in the South African mining sector. Tharisa Minerals complies with the requirements of the Mining Charter. The Mining Charter III was gazetted on 15 June 2017. The Group is studying and assessing the regulations and the way forward to ensure compliance. Tharisa remains committed to transformation in the mining industry.
Outlook
PGM and chrome production remains on track to meet the FY2017 production guidance of approximately 147.4 koz PGMs on a 6E basis and 1.3 Mt chrome concentrates, of which 300 kt will be specialty grade chrome concentrates.
The above information has not been reported on or reviewed by Tharisa's auditors.
Paphos, Cyprus
10 July 2017
JSE Sponsor
Investec Bank Limited
Investor Relations contact:
Tharisa plc
Sherilee Lakmidas
+27 11 996 3538
+27 79 276 2529
slakmidas@tharisa.com
Broker contacts:
Peel Hunt LLP (Joint Broker)
Matthew Armitt / Ross Allister
+44 207 7418 8900
BMO Capital Markets Limited (Joint Broker)
Jeffrey Couch/Neil Haycock/Thomas Rider
+44 020 7236 1010
Financial PR contacts:
Bobby Morse/Anna Michniewicz
+44(0) 20 7466 5000
tharisa@buchanan.uk.com
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCEANXXESLXEEF
(END) Dow Jones Newswires
July 10, 2017 02:00 ET (06:00 GMT)
1 Year Tharisa Chart |
1 Month Tharisa Chart |
It looks like you are not logged in. Click the button below to log in and keep track of your recent history.
Support: +44 (0) 203 8794 460 | support@advfn.com
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions