ADVFN Logo ADVFN

We could not find any results for:
Make sure your spelling is correct or try broadening your search.

Trending Now

Toplists

It looks like you aren't logged in.
Click the button below to log in and view your recent history.

Hot Features

Registration Strip Icon for default Register for Free to get streaming real-time quotes, interactive charts, live options flow, and more.

KIBO Kibo Energy Plc

0.0375
0.00 (0.00%)
19 Apr 2024 - Closed
Delayed by 15 minutes
Share Name Share Symbol Market Type Share ISIN Share Description
Kibo Energy Plc LSE:KIBO London Ordinary Share IE00B97C0C31 ORD EUR0.0001 (CDI)
  Price Change % Change Share Price Bid Price Offer Price High Price Low Price Open Price Shares Traded Last Trade
  0.00 0.00% 0.0375 0.035 0.04 0.0375 0.036 0.0375 0.00 08:00:03
Industry Sector Turnover Profit EPS - Basic PE Ratio Market Cap
Gold Ores 1.04M -9.78M -0.0026 -0.15 1.51M

Katoro Gold PLC Imweru Drill Programme Ahead of Schedule (8114K)

12/07/2017 7:00am

UK Regulatory


Kibo Energy (LSE:KIBO)
Historical Stock Chart


From Apr 2019 to Apr 2024

Click Here for more Kibo Energy Charts.

TIDMKAT TIDMKIBO

RNS Number : 8114K

Katoro Gold PLC

12 July 2017

Katoro Gold plc (Incorporated in England and Wales)

(Registration Number: 9306219)

Share code on AIM: KAT

ISIN: GB00BSNBL022

("Katoro" or "the Company")

12 July 2017

Imweru Drill Programme Ahead of Schedule and Below Budget

Katoro Gold plc ("Katoro" or the "Company") (AIM: KAT), the Tanzania focused gold exploration and development company, is pleased to announce that the infill drilling programme on its Imweru gold project in Tanzania is progressing significantly better than planned and is currently ahead of schedule and below budget.

Highlights

 
      --      Significant cost savings achieved, allowing 
               scope of the Imweru development plan to be 
               expanded to include: 
               o Commissioning of full environmental and 
               social impact assessment study ("ESIA") - 
               no additional fundraise now required to conduct 
               the ESIA 
               o Imweru development drill program expanded 
               to add additional 2,000 metres to the original 
               drill program of approximately 1,400 metres 
      --   Expanded drill program 75% complete - now 
            approximately 10 days ahead of schedule in 
            addition to two months gained on mobilisation 
            (See RNS of 15 June 2017) 
      --   Katoro set to be first successful exporter 
            of geological samples under new mining legislation 
 

As a result, of the strong drill performance and significant cost savings made in the last two weeks, Katoro has been able to change and expand the scope of the original Imweru development plan. The Company now has the budget to:

 
      --   Commission the full ESIA without the need 
            to raise additional funds as originally stated 
            in its Admission Document. The ESIA has already 
            commenced and is fully mobilised 
      --   Expand the original drill program to a total 
            of 31 drill holes (3,410 metres), as opposed 
            to the original 8 to 10 holes (1,400 metres). 
            The additional metres will also include the 
            water drilling program that is required to 
            complete the hydrological study which constitutes 
            part of the ESIA 
 

The full complement of metallurgical samples required for the Imweru Feasibility Study are currently in the process of being exported to South Africa for analysis. These are the first geological samples to be exported under the new mining rules and whilst it is a more cumbersome process, no significant delays have been encountered to date nor are there any anticipated at this stage.

Louis Coetzee, Executive Chairman of Katoro commented: "We are extremely pleased with progress on the Imweru development programme. This, combined with the vast in-country experience of the technical teams, has put the Company in a strong position to extract substantially more value out of the approved work program than initially expected. The fact that the full ESIA can now be conducted in parallel to the Feasibility Study will enable the Company to submit a far more complete and technically sound mining right application, which the Company believes will significantly expedite the application process. The expanded drill program will make an invaluable contribution towards enhancing the integrity of the Imweru resource both quantitatively and qualitatively, whilst simultaneously allowing the Company to complete all the geotechnical and hydrological work required for the Imweru Feasibility Study."

Contacts

 
 Louis Coetzee    +27 (0) 83   Katoro Gold plc       Executive 
                   2606126                            Chairman 
---------------  -----------  --------------------  ----------- 
 Jon Belliss      +44 (0) 20   Beaufort Securities   Broker 
                   7382 8300    Limited 
---------------  -----------  --------------------  ----------- 
 Richard          +44 (0) 20   Strand Hanson         Nominated 
  Tulloch          7409 3494    Limited               Adviser 
  Ritchie 
  Balmer 
  Frederick 
  Twist 
---------------  -----------  --------------------  ----------- 
 Liz Morley       +44 (0) 20   Bell Pottinger        Investor 
  Molly Stewart    3772 2500                          and Media 
                                                      Relations 
---------------  -----------  --------------------  ----------- 
 

Katoro Gold - Notes to editors

In May 2017 Katoro acquired the Imweru and Lubando Gold Projects in Tanzania from Kibo Mining plc for a total consideration of GBP3.66 million and was admitted to trading on AIM.

Following the acquisition, Katoro owns 100% of the Imweru and Lubando Projects, which both have Mineral Resources established in accordance with the JORC (2012) Code. The total Mineral Resources stated for Imweru consist of 11.607 Mt at grade of 1.38 g/t for a Mineral Resource of 515,110 oz Au at a resource pay limit of 0.4 g/t for the open pittable material and 1.3 g/t for the underground material, while the Lubando Mineral Resources equate to 6.78 Mt at grade of 1.10 g/t for 239,870 oz Au at a pay limit of 0.4 g/t to a depth of 200 m and 1.3 g/t below the 200 m depth cut-off. The respective projects also include the earlier stage Sheba (within the Imweru Licence Portfolio and Imweru Option Portfolio), Pamba and Busolwa (both within the Lubando Licence Portfolio and Lubando Option Portfolio) projects. The JORC Code compliant Competent Person's Report for each of Imweru and Lubando are available on Katoro's website www.katorogold.com.

The Company's primary focus is on advancing and developing Imweru through a work programme which will include, inter alia, a feasibility study and a drilling programme, with the aim, subject to funding, to commence production with an initial target of 50,000 oz gold per annum within 18-24 months from admission to AIM.

Updates on the Katoro's activities will be posted on its website www.katorogold.com.

This announcement contains inside information as stipulated under the Market Abuse Regulations (EU) no. 596/2014 ("MAR").

This information is provided by RNS

The company news service from the London Stock Exchange

END

MSCELLBFDDFZBBZ

(END) Dow Jones Newswires