ADVFN Logo ADVFN

We could not find any results for:
Make sure your spelling is correct or try broadening your search.

Trending Now

Toplists

It looks like you aren't logged in.
Click the button below to log in and view your recent history.

Hot Features

Registration Strip Icon for discussion Register to chat with like-minded investors on our interactive forums.

EML Emmerson Plc

2.00
0.00 (0.00%)
Last Updated: 08:00:00
Delayed by 15 minutes
Share Name Share Symbol Market Type Share ISIN Share Description
Emmerson Plc LSE:EML London Ordinary Share IM00BDHDTX83 ORD NPV
  Price Change % Change Share Price Bid Price Offer Price High Price Low Price Open Price Shares Traded Last Trade
  0.00 0.00% 2.00 1.90 2.10 2.00 2.00 2.00 200,000 08:00:00
Industry Sector Turnover Profit EPS - Basic PE Ratio Market Cap
Crude Petroleum & Natural Gs 0 -3.2M -0.0031 -6.45 20.53M

Emmerson PLC Potential for Very Low Capital Cost Port Upgrade (9748G)

12/11/2018 7:00am

UK Regulatory


Emmerson (LSE:EML)
Historical Stock Chart


From Apr 2019 to Apr 2024

Click Here for more Emmerson Charts.

TIDMEML

RNS Number : 9748G

Emmerson PLC

12 November 2018

Emmerson Plc / Ticker: EML / Index: LSE / Sector: Mining

12 November 2018

Emmerson Plc ("Emmerson" or the "Company")

Potential for Very Low Capital Cost Port Upgrade for Khemisset Potash Project and Scoping Study Progressing Ahead of Schedule

Emmerson Plc, the Moroccan focused potash development company, is pleased to announce that it has completed the preliminary design and cost estimates for the port upgrade necessary to allow the export of potash product at the Port of Mohammedia from the Company's 100% owned Khemisset Potash Project located in northern Morocco ("Khemisset" or "the Project"). This work has been completed by independent Moroccan engineering consultant, Sigma Plus ("Sigma"), a sub-consultant, as part of the forthcoming Scoping Study which is due to be released in the near-term. The completed estimates have confirmed the potential for further significant capital cost savings for the Project.

In an update to previous guidance, the Company now expects the Scoping Study to be published in Q4 2018, well ahead of schedule.

To view the press release with the illustrative maps and diagrams please use the following link:

http://www.rns-pdf.londonstockexchange.com/rns/9748G_1-2018-11-11.pdf

Highlights

-- Total budgeted cost for construction of port upgrades is approximately US$7.5 million including a 30% contingency

-- Initial discussions with local authorities indicate that the Port of Mohammedia (150km from proposed mine site) has capacity for exports from Khemisset

-- Port of Casablanca and proposed Port of Kenitra expected to present feasible alternative options

-- Estimated capital cost saving of approximately 95% for capex cost for port upgrade, or over US$190 million, relative to cost of a recently constructed potash handling port facility in Canada[1]

   --   Design and estimate completed according to AusIMM guidelines for capital cost estimates 

-- Further enhances Management's strong belief in potential for Khemisset to be a low capital cost potash mine development, following the announcements of low capex mine access, low capex logistics solution, and low capex electrical and gas supply which combined have the potential to save Emmerson over US$1.2 billion when compared to benchmark projects (refer RNS's dated 18 September, 08 October, and 23 October 2018)

   --   Scoping Study to be delivered in Q4 2018, well ahead of previous schedule 

Hayden Locke, CEO of Emmerson, commented:

"The Khemisset Project benefits from its proximity to a number of existing and planned port options when the Project commences production. Access to existing port facilities, with minimal upgrades required, result in significant capital cost savings for the Project. Morocco has invested heavily in all facets of infrastructure, including world-class ports, which are already resulting in significant benefits for Emmerson.

"Our initial discussions with authorities at the Port of Mohammedia have confirmed that there is expected to be capacity for the export of potash produced from Khemisset. Cost estimates include construction of a storage warehouse and loading facility for the handling of at least 800,000 tonnes of potash product per annum.

"The already completed design and cost estimates for the access to mineralisation, connection to logistics, and connection to electricity and gas supply and port facilities have highlighted the significant cost savings available to the Khemisset Project, which are estimated to amount to over US$1.2 billion compared to Canadian peers. This announcement further enhances our belief that the Scoping Study for Khemisset will present a low capital cost, high margin proposition which should result in compelling economic metrics.

"The Scoping Study is well ahead of schedule and we are excited to release the results to the market as soon as it is finalised, which we expect to be imminently."

Comparison to Peers

The Scoping Study port upgrade design and costing for the Khemisset Project, completed by independent engineers Sigma, indicates that the capital cost requirement to upgrade port facilities should be far lower than the equivalent port upgrade capex costs for other potash projects globally. A comparison to other potash projects is shown in Figure 1 below

Figure 1. Capital costs for Port Build or Upgrade in selected potash projects

Port Upgrade Overview

Sigma, which was appointed by the Company to design and cost an initial facility at port, has completed basic design and cost estimates for the port upgrade. Designs and estimates have been prepared in line with Scoping Study guidelines provided by the Australasian Institute of Mining and Metallurgy ("AusIMM").

Basis of Port Upgrade

The Company has instructed Sigma to design a facility at port which will include:

   -      Facilities to unload potash from trucks at 500t/h 
   -      A warehouse with capacity of 25,000 tonnes 
   -      Loading facilities from the warehouse onto ships at 1,000 t/h 

- Able to receive, unload and reload at least 800,000 tonnes per annum depending on truck and ship frequency

Sigma has prepared preliminary design and costings based on these requirements.

Figures 2 and 3 below demonstrate the designed facilities.

Figure 2. Cross section of designed warehouse with Roof Mounted Stacker

Figure 3. Cross section of reclaim and ship loading facilities

Cost Estimation

The total budgeted capital cost required to upgrade the port facilities to allow export of product is US$7.5 million including a 30% contingency. Cost estimation for the port upgrade has been conducted in line with Scoping Study levels of accuracy of approximately +/-30-50%.

A summary of the cost breakdown is presented in Table 1 below:

 
 Item                                          US$ millions 
------------------------------  --------------------------- 
 Warehouse                                             $2.2 
------------------------------  --------------------------- 
 Truck Unloading Equipment                             $1.5 
------------------------------  --------------------------- 
 Ship Loading Equipment                                $2.1 
------------------------------  --------------------------- 
 Contingency (30%)                                     $1.7 
------------------------------  --------------------------- 
 Total Direct Costs including 
  Contingency                                          $7.5 
------------------------------  --------------------------- 
 

Table 1: Summary of Direct Costs for Port Upgrade Capex

 
 For further information, please visit www.emmersonplc.com, follow 
  us on Twitter (@emmerson_plc), or contact:                    Emmerson Plc                Tel: +44 (0) 207 236 
   Hayden Locke                                    1177 
   Edward McDermott 
   James Biddle       Beaumont Cornish Limited    Tel: +44 (0) 207 628 
    Roland Cornish     Financial Adviser           3396 
   Jeremy King        Optiva Securities Limited   Tel: +44 (0) 3137 1904 
                       Broker 
 
   Lottie Wadham      St Brides Partners Ltd      Tel: +44 (0) 20 7236 
    Gaby Jenner        Financial PR/IR             1177 
 

**ENDS**

Notes to Editors

Emmerson's primary focus is on developing the Khemisset Potash Project located in Northern Morocco. The project has a large JORC Resource Estimate (2012) of 311.4Mt @ 10.2% K(2) O and significant exploration potential with an accelerated development pathway targeting a low capex, high margin mine. Khemisset is perfectly located to capitalise on the expected growth of African fertiliser consumption whilst also being located on the doorstep of European markets. This unique positioning means the project will receive a premium netback price compared to existing potash producers. The need to feed the world's rapidly increasing population is driving demand for potash and Emmerson is well placed to benefit from the opportunities this presents.

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014.

[1] Based on Pacific Coast Terminals Co. Ltd. Project Environmental Review Document for K+S Canada Port Moody Potash Handling and Storage System, 3 February 2015 (http://pct.ca/wp-content/uploads/2014/12/PCT-Potash-Project-Environmental-Review-Document-FINAL.pdf) excluding contingency.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

END

MSCBBBITMBTBBMP

(END) Dow Jones Newswires