ADVFN Logo ADVFN

We could not find any results for:
Make sure your spelling is correct or try broadening your search.

Trending Now

Toplists

It looks like you aren't logged in.
Click the button below to log in and view your recent history.

Hot Features

Registration Strip Icon for alerts Register for real-time alerts, custom portfolio, and market movers

BMN Bushveld Minerals Limited

0.625
-0.025 (-3.85%)
Last Updated: 10:16:02
Delayed by 15 minutes
Share Name Share Symbol Market Type Share ISIN Share Description
Bushveld Minerals Limited LSE:BMN London Ordinary Share GG00B4TM3943 ORD 1P
  Price Change % Change Share Price Bid Price Offer Price High Price Low Price Open Price Shares Traded Last Trade
  -0.025 -3.85% 0.625 0.60 0.65 0.65 0.625 0.65 5,263,685 10:16:02
Industry Sector Turnover Profit EPS - Basic PE Ratio Market Cap
Minrls,earths-ground,treated 151.18M -38.97M -0.0166 -0.37 14.53M

Bushveld Minerals Limited Q3 and 9 months 2021 Operational Update (7418P)

21/10/2021 7:00am

UK Regulatory


Bushveld Minerals (LSE:BMN)
Historical Stock Chart


From Apr 2021 to Apr 2024

Click Here for more Bushveld Minerals Charts.

TIDMBMN

RNS Number : 7418P

Bushveld Minerals Limited

21 October 2021

Market Abuse Regulation ("MAR") Disclosure

This announcement contains inside information for the purposes of Article 7 of the Market Abuse Regulation (EU) 596/2014 as it forms part of UK domestic law by virtue of the European Union (Withdrawal) Act 2018 ("MAR"), and is disclosed in accordance with the Company's obligations under Article 17 of MAR.

21 October 2021

Bushveld Minerals Limited

("Bushveld Minerals" "Bushveld" or the "Company")

Q3 and 9 months 2021 Operational Update

Bushveld Minerals Limited (AIM: BMN), the AIM quoted, integrated primary vanadium producer and energy storage solutions provider with ownership of high-grade assets in South Africa, is pleased to provide an operational update for the three months and nine months ending 30 September 2021 ("Q3 2021 and 9M 2021").

Key Highlights

Bushveld Vanadium

-- Q3 2021 Total Injury Frequency Rate ("TIFR") of 8.74, an improvement of 46 per cent on Q3 2020 (Q3 2020: 16.10).

-- Group production in Q3 2021 of 1,056 mtV, an increase of 19 per cent on Q2 2021 (Q2 2021: 886 mtV), underpinned by continued operational stability at Vametco.

- Focus has been on stabilising operations to achieve a sustainable production run rate supported by the implementation of a proactive maintenance programme, other operational improvements and a new operating model at both plants.

- Vametco's production cash cost (C1) of US$22.4/kgV improved by 13 per cent on Q2 2021, as a result of the higher throughput in Q3 2021 and a weaker ZAR:USD exchange rate.

- Vanchem production cash cost (C1) of US$27.3/kgV improved by three per cent on Q2 2021, in line with the weaker ZAR:USD exchange rate.

-- Group production for 9M 2021 of 2,629 mtV, was two per cent lower than 9M 2020 Group production of 2,680 mtV, as a result of lower production volumes at Vametco during the H1 2021.

   --      On track to meet 2021 Group production guidance of between 3,400 mtV and 3,600 mtV. 

-- Unit costs for this 9M 2021 have started to normalise in line with the lower unit costs in Q3 2021 on the back of the higher throughput, and we expect this trend to continue in Q4 2021. We are therefore maintaining our unit cash cost guidance for 2021 at both plants.

-- Group sales in Q3 2021 of 826 mtV(1) in line with Q2 2021 of 820 mtV. Despite higher production volumes, sales to final customers were impacted by challenges in international logistics channels arising from COVID-19 , the unrest in South Africa in July 2021 as well as disruptions at local ports in July and August 2021. We expect sales to recover as warehouse stocks in target markets are replenished.

1: Reported as final sales to customers.

Finance update

-- Positive progress has been made in negotiations with Duferco Participations Holding S.A ("Duferco") on the remaining balance US$11.5 million of the convertible loan note, that would result in US$5 million being payable in November 2021 and the remaining US$6.5 million being converted into Bushveld shares , as announced on 27 September 2021 . We will update the market in due course on the final outcome.

-- Cash and cash equivalents as at 30 September 2021 of US$25 million (30 June 2021: US$31.6 million) was impacted by the lower sales and the consequential higher working capital, as well as the on-going capital expenditure during the quarter to support growth and operational stability.

Vanadium market

-- After a strong start to the quarter, Ferrovanadium prices ("FeV") fell and currently trade at an average of approximately US$31/kgV across markets. At the moment, the US market is maintaining a premium to European prices with Chinese prices marginally lower.

   --      Demand in the US, Europe and Rest of the world remains buoyant. 

-- Q3 2021 London Metal Bulletin FeV price averaged US$38.2/kgV, 6 per cent higher than Q2 2021 (US$36.0/kgV) and 58 per cent higher than Q3 2020 (US$24.2/kgV).

-- The 2021 year to date average FeV price is approximately US$35/kgV across all markets as at 8 October 2021.

Fortune Mojapelo, CEO of Bushveld Minerals Limited, commented:

"I am pleased to report a solid quarter of production where we achieved our targets of stability and cost control at both our operations, on the back of the operational improvements we are implementing. At the same time, we were able to improve safety statistics, a very important achievement and one we will continue to focus on.

"We entered Q4 2021 on a strong footing as a result and therefore still on track to achieve our production guidance. We continue to invest in sustaining and growth capital to maintain stability and provide the platform for growth, to support the volume increase in 2022."

Conference call

Bushveld Minerals Chief Executive Officer, Fortune Mojapelo, Finance Director, Tanya Chikanza and Francois Naude, Director of Operations; will host a conference call at 11:00 am UK time (12:00 noon SAST) today to discuss the quarterly update with analysts. Participants may join the call by dialling:

   Tel:                   United Kingdom: +44 (0) 330 336 9434; South Africa: +27 11 844 6054 
   Pin:                  6605060 

A replay of the conference call will be available on the Company's website post the call.

Safety and COVID-19

-- Q3 2021 Total Injury Frequency Rate ("TIFR") of 8.74, an improvement of 46 per cent on Q3 2020 of 16.10, as a result of increased planned task observations by supervisors and proactively applying lessons learned from previous incidents.

-- From 1 October 2021, South Africa's lockdown regulations were relaxed to an adjusted level 1 as the country exited the third wave of COVID-19 and to ensure economic recovery. Bushveld Minerals is encouraged with the progress of the vaccination awareness at the operations.

Bushveld Vanadium

 
                                                       Q3 2021    Q3 2021    9M 2021 
                                                          vs         vs         vs 
 Group          Unit     Q3 2021   Q2 2021   9M 2021    Q2 2021    Q3 2020    9M 2020 
 Production    mtV(1)     1,056      886      2,629     19.0%       3.6%      -1.9% 
              --------  --------  --------  --------  ---------  ---------  --------- 
 Sales         mtV(1)      826       820      2,434      0.7%       0.4%      -6.0% 
              --------  --------  --------  --------  ---------  ---------  --------- 
 
   1.     mtV = metric tonnes of vanadium. 

Vametco

Table 1: Operational highlights for Vametco (on a 100% basis)(1)

 
                                                               Q3 2021   Q3 2021   9M 2021 
                                                                  vs        vs        vs 
 Description              Unit     Q3 2021  Q2 2021   9M 2021   Q2 2021   Q3 2020   9M 2020 
 Ore mined               Tonnes    339 556  192,868   846 997   76.1%     -23.0%    -11.1% 
                         -------  --------  -------  --------  --------  --------  -------- 
                                                       2 248 
 Total mined             Tonnes    782 636  848,858     607     -7.8%     -11.2%    36.9% 
                         -------  --------  -------  --------  --------  --------  -------- 
 Ore grade (in           % V(2) 
  whole rock)              O(5)     0.82     0.75       0.7      9.3%     34.4%     14.8 % 
                         -------  --------  -------  --------  --------  --------  -------- 
 Concentrate produced    Tonnes    113 683  90,907    282 048   25.1%     17.0%     -2.3% 
                         -------  --------  -------  --------  --------  --------  -------- 
 Concentrate grade         % V      1.07     1.07      1.06       -        3.9%      2.9% 
                         -------  --------  -------  --------  --------  --------  -------- 
 Recovery from 
  Kiln to MVO(2)            %       75.3     66.3      72.0     13.6%      2.3%      0.9% 
                         -------  --------  -------  --------  --------  --------  -------- 
 Production (Nitrovan, 
  FeV)                   mtV(3)      765      593      1 753    28.9%      5.6%     -10.1% 
                         -------  --------  -------  --------  --------  --------  -------- 
 Production cash 
  cost (C1) (4)          ZAR/KgV     327      364       355     -10.1%     7.0%     21.6% 
                         -------  --------  -------  --------  --------  --------  -------- 
 Production cash 
  cost (C1) (4)          US$/KgV    22.4     25.8      24.4     -13.2%    23.8%     39.4% 
                         -------  --------  -------  --------  --------  --------  -------- 
 Foreign exchange 
  rate                   ZAR:USD    14.62    14.14     14.57     3.4%     -13.6%    -12.4% 
                         -------  --------  -------  --------  --------  --------  -------- 
 

1. Based on provisional, unaudited figures. Bushveld's net attributable interest of the above figures is approximately 74 per cent. Production cash cost is based on vanadium produced.

2. Recoveries were up by 13.6 percent in Q3 2021 relative to Q2 2021, as Q2 2021 was impacted by April slower start-up.

   3.     mtV = metric tonnes of vanadium. 

4. Excludes depreciation, royalties and selling, general & administrative expenses and cost associated with COVID-19. Production cash cost is based on vanadium produced. Production cash cost (C1) measure does not have any standardized meaning prescribed by IFRS and differs from measures determined in accordance with IFRS. This measure is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. This measure is not necessarily indicative of net earnings or cash flow from operating activities as determined under IFRS.

-- Q3 2021 production of 765 mtV was 29 per cent higher than Q2 2021 of 593 mtV, underpinned by continued operational stability and improved plant performance.

- Since the successful completion of maintenance work in H1 2021, steady performance continued in Q3 2021 resulting in July, August, and September production of 251 mtV, 260 mtV and 254 mtV respectively.

-- 9M 2021 production of 1,753 mtV was 10 per cent lower than 9M 2020 of 1,951 mtV, due to plant instability, planned 35-day maintenance and unprotected industrial action in the first four months of H1 2021.

-- Q3 2021 production cash cost (C1) of US$22.4/kgV was 13 per cent lower than Q2 2021 of US$25.8/kgV, as a result of higher volumes in Q3 2021. The net impact of the higher volumes and increased costs in ZAR, reduced unit cost by 10 per cent and the slightly weaker exchange rate of USD:ZAR14.62 relative to Q2 2021 of USD:ZAR14.14 reduced unit cost by a further three per cent.

-- 9M 2021 production cash cost (C1) of US$24.4/kgV was 39 per cent higher relative to 9M 2020 of US$17.5/kgV, due to lower production volumes and a stronger ZAR:USD exchange rate. The net impact of the volume decrease and increase in cost of production was to increase unit costs by 22 per cent, while the stronger ZAR:USD exchange rate increased unit costs by a further 17 per cent.

-- 2021 production guidance maintained to between 2,300 mtV and 2,400 mtV, and production cash cost (C1) of between US$23.70/kgV and US$24.20/kgV (ZAR339/kgV and ZAR345/kgV).

Vanchem

Table 2: Operational highlights for Vanchem(1)

 
                                                                     Q3 2021   Q3 2021   9M 2021 
                                                                        vs        vs        vs 
 Description                    Unit     Q3 2021  Q2 2021   9M 2021   Q2 2021   Q3 2020   9M 2020 
 Ore mined                     Tonnes    53 241   40 708    141 255   30.8%     20.0%      1.6% 
                               -------  --------  -------  --------  --------  --------  -------- 
 Ore Grade (in Whole           % V(2) 
  Rock)                          O(5)     1.45     1.36      1.39      6.6%      2.8%     -2.1% 
                               -------  --------  -------  --------  --------  --------  -------- 
 Concentrate produced          Tonnes    37 511   26 300    97 160    42.6%     -1.9%     -19.5% 
                               -------  --------  -------  --------  --------  --------  -------- 
 Concentrate Grade               % V      0.92     0.95      0.94     -3.2%     -5.2%       - 
                               -------  --------  -------  --------  --------  --------  -------- 
 Vametco concentrate 
  to kiln                      Tonnes     5 501    5 750    16 484    -4.3%      100%      100% 
                               -------  --------  -------  --------  --------  --------  -------- 
 Recovery: Kiln to 
  Final Product                   %       75.6     89.9      81.8     -15.6%    -13.4%    13.9% 
                               -------  --------  -------  --------  --------  --------  -------- 
 Chemicals                     mtV(2)      92       87        179      5.0%      100%     173.5% 
                               -------  --------  -------  --------  --------  --------  -------- 
 Flake                         mtV(2)      59       66        258     10.9%     -66.2%    -31.7% 
                               -------  --------  -------  --------  --------  --------  -------- 
 FeV                           mtV(2)      140      120       305     16.6%     17.2%      6.7% 
                               -------  --------  -------  --------  --------  --------  -------- 
 Nitrovan                      mtV(2)       -       19        135     -100%       -         - 
                               -------  --------  -------  --------  --------  --------  -------- 
 Total production              mtV(2)      291      293       876     -0.3%     -1.0%     20.2% 
                               -------  --------  -------  --------  --------  --------  -------- 
 Weighted average production 
  cash cost (C1)(3)            ZAR/kgV     399      398       419      0.3%     -20.9%    -11.8% 
                               -------  --------  -------  --------  --------  --------  -------- 
 Weighted average production 
  cash cost (C1)(3)            US$/kgV    27.3     28.1      28.7     -2.8%     -8.4%      1.1% 
                               -------  --------  -------  --------  --------  --------  -------- 
 Foreign exchange rate         ZAR:USD    14.62    14.14     14.57     3.4%     -13.6%    -12.4% 
                               -------  --------  -------  --------  --------  --------  -------- 
 
   1.     Based on provisional, unaudited figures. 
   2.     mtV = metric tonnes of vanadium. 

3. Excludes depreciation , royalties and selling, general & administrative expenses and cost associated with Covid-19. Production cash cost is based on vanadium produced. Production cash cost (C1) measure does not have any standardized meaning prescribed by IFRS and differs from measures determined in accordance with IFRS. This measure is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. This measure is not necessarily indicative of net earnings or cash flow from operating activities as determined under IFRS.

   --      Q3 2021 production of 291 mtV in line with Q2 2021 of 293 mtV and Q3 2020 of 294 mtV. 

-- 9M 2021 production of 876 mtV was 20 per cent higher than 9M 2020 production of 729 mtV. The lower 9M 2020 production was impacted by the shutdown of Kiln 1 for just over a month due to COVID-19 pandemic.

-- Q3 2021 production cash cost (C1) of US$27.3/kgV was three per cent lower than Q2 2021 of US$28.1/kgV, as a result of the slightly weaker exchange rate of USD:ZAR14.62 relative to Q2 2021 of USD:ZAR14.14. The Q3 2021 production cash cost (C1) in local currency of ZAR398.8/kgV was in line with the Q2 2021 of ZAR397.8/kgV).

-- 9M 2021 production cash cost (C1) in local currency of ZAR418.6/kgV, was 12 per cent lower than 9M 2020 of ZAR474.5/kgV due to the higher volumes produced. The strong ZAR:USD exchange rate movement then reversed this improvement, and as a result, the 9M 2021 production cash cost (C1) of US$28.7/kgV was in line with 9M 2020 of US$28.4/kgV.

-- 2021 production guidance maintained to between 1,100 mtV and 1,200 mtV, and production cash cost (C1) of between US$30.3/kgV and US$31.1/kgV (ZAR434/kgV and ZAR444/kgV) .

Growth Projects

Vametco Phase III P re-feasibility studies ("PFS")

As previously announced on 30 June 2021, the scope of work of the PFS for Phase III at Vametco has been extended to include upgrading the concentrate section to a Semi-Autogenous Grinding mill and life of mine of Open Pit with higher production to supply both Vametco and Vanchem, making Vametco the single ore supply for both operations for the medium-term. Details on the ramp-up profile and capital expenditure plans will be provided once the PFS has been completed, which is still expected in Q4 2021.

Vanchem Phase II refurbishment

Vanchem's production is expected to increase from 1,100 mtV to a run rate of 2,600 mtV by the end of 2022, supported by the commissioning of Kiln 3 and associated downstream expansions. Vanchem has three roasting kilns of which Kiln 3 holds similar properties to that of Vametco's Kiln. It has a length of 90 metres and 4.0m in diameter and covers 50 per cent of Vanchem's installed kiln roasting capacity, with Kiln 2 and Kiln 1 at 25 per cent respectively.

The Upper Seam Project

The Upper Seam project continues with commissioning. All crushing units have been commissioned and are operational, with the magnetic separator to be commissioned at the end of October 2021. Vanchem has received the initial batches of ore from the Upper Seam Project.

The Upper Seam Project has a reserve of 0.9 Mt of in-situ ore and the total resource base of 16 Mt. The resource has similar mineralogy to the current ore used at Vanchem, and tests conducted have proven its suitability for processing. This will ensure that Vanchem has sufficient ore feedstock in the short to medium term, with no significant capital expenditure requirements.

Bushveld Vanadium production profile

-- Bushveld Vanadium is targeting to materially grow its vanadium production and achieve an annualised steady state production run rate of between 5,000 mtVp.a. and 5,400 mtVp.a. by the end of 2022.

- We continue to prioritise operational stability at Vametco to achieve a sustainable and consistent output of 2,800 mtVp.a.

- Vanchem's production run rate is expected to more than double from 1,100 mtVp.a. to a run rate of 2,600 mtVp.a. by the end of 2022, supported by the commissioning of Kiln 3 and associated downstream expansions. Kiln-3 is expected to be commissioned in H1 2022.

S

Enquiries: info@bushveldminerals.com

 
                                                          +27 (0) 11 268 
Bushveld Minerals Limited                                  6555 
Fortune Mojapelo, Chief Executive 
 Officer 
Andrew Mari, Investor Relations 
 
                                      Nominated Adviser   +44 (0) 20 3470 
SP Angel Corporate Finance LLP         & Broker            0470 
Richard Morrison / Charlie Bouverat 
Grant Baker / Richard Parlons 
 
                                                          +44 (0) 20 7418 
Peel Hunt Limited                     Joint Broker         8900 
Ross Allister / Alexander Allen 
 
Tavistock                             Financial PR 
Gareth Tredway / Tara Vivian-Neal/                        +44 (0) 207 920 
 Adam Baynes                                               3150 
 

ABOUT BUSHVELD MINERALS LIMITED

Bushveld Minerals is a low-cost, vertically integrated primary vanadium producer. It is one of only three operating primary vanadium producers, owning 2 of the world's 4 operating primary vanadium processing facilities. In 2020, the Company produced more than 3,600 mtV, representing approximately three per cent of the global vanadium market. With a diversified vanadium product portfolio serving the needs of the steel, energy and chemical sectors, the Company participates in the entire vanadium value chain through its two main pillars: Bushveld Vanadium, which mines and processes vanadium ore; and Bushveld Energy, an energy storage solutions provider. Bushveld Vanadium is targeting to materially grow its vanadium production and achieve an annualised steady state production run rate of between 5,000 mtVp.a. and 5,400 mtVp.a by the end of 2022, from projects currently being implemented. Beyond that, pre-feasibility studies are in progress to determine the optimal path to increase production even further to a steady state production run rate of between 6,400 mtVp.a. and 6,800 mtVp.a. in the medium-term and to a steady state production run rate of 8,400 mtVp.a in the long term.

Bushveld Energy is focused on developing and promoting the role of vanadium in the growing global energy storage market through the advancement of vanadium-based energy storage systems, specifically Vanadium Redox Flow Batteries ("VRFBs").

Detailed information on the Company and progress to date can be accessed on the website www.bushveldminerals.com

About Vametco

Vametco is located near Brits on the Western Limb of the Bushveld Complex. The integrated operation comprises a vanadium ore mine and a processing plant that produces mostly Nitrovan, a trademark product sold in major steel markets across the world. The mine lies adjacent to the Brits Vanadium Project, which will in future serve as an alternative source of near surface run of mine ("ROM") ore feed to the Vametco plant.

The Vametco mining operation uses open pit bench mining methods to mine a well-defined orebody. The deposit is continuous with limited faulting and dips in a northerly direction at approximately 19 degrees.

ROM ore is fed into a primary, secondary and tertiary crushing circuit, followed by milling and magnetic separation to produce magnetite concentrates. The magnetite concentrates are fed into the extraction process which includes the kiln for roasting followed by leaching and precipitation. Thereafter the precipitated vanadium as ammonium metavanadate is converted to modified vanadium oxide ("MVO") in rotary calciners. MVO is fed into the mix plant and finally into the shaft furnaces to produce Nitrovan.

About Vanchem

Vanchem is situated at Ferrobank Industrial Park in Emalahleni Local Municipality, Mpumalanga Province in the Republic of South Africa. Vanchem is a primary vanadium producing facility with a beneficiation plant capable of producing various vanadium oxides, ferrovanadium and vanadium chemicals. Vanchem uses the salt roast beneficiation process, similar to the one used at Vametco. The plant comprises: a core salt-roast processing plant, including 3 roasting kilns, an electric smelting ferrovanadium converter, an alumino-thermic smelting facility, also located at Highveld, a vanadium chemical plant; and a rail siding linking the plant with Bushveld deposits and additional potential supply sources through the national rail network.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.

END

UPDEAFEEADDFFAA

(END) Dow Jones Newswires

October 21, 2021 02:00 ET (06:00 GMT)

1 Year Bushveld Minerals Chart

1 Year Bushveld Minerals Chart

1 Month Bushveld Minerals Chart

1 Month Bushveld Minerals Chart

Your Recent History

Delayed Upgrade Clock